File #: ID 22-59    Version: 1 Name:
Type: Action Item Status: Passed
File created: 12/27/2021 In control: City Council
On agenda: 1/13/2022 Final action: 1/13/2022
Title: Approve Fourth Amendment to the Consultant Services Agreement, dated January 2, 2019, with Blair, Church, and Flynn Consulting Engineers, Inc., in the amount of $55,400, increasing the total contract amount to $268,179.72, for the Midtown Fresno Trail Project on the north bank of the Mill Ditch along McKinley Avenue from Millbrook Avenue to Clovis Avenue (Council Districts 4 & 7).
Sponsors: Public Works Department
Attachments: 1. 22-59 Fourth Admendment.pdf, 2. 22-59 Location Map.pdf, 3. 22-59 Vicinity Map.pdf
REPORT TO THE CITY COUNCIL


FROM: SCOTT L. MOZIER, PE, Director
Public Works Department

BY: RANDALL W. MORRISON, PE, Assistant Director
Public Works Department, Engineering Division

JASON MILLER, PE, Supervising Professional Engineer
Public Works Department, Engineering Division

SUBJECT
Title
Approve Fourth Amendment to the Consultant Services Agreement, dated January 2, 2019, with Blair, Church, and Flynn Consulting Engineers, Inc., in the amount of $55,400, increasing the total contract amount to $268,179.72, for the Midtown Fresno Trail Project on the north bank of the Mill Ditch along McKinley Avenue from Millbrook Avenue to Clovis Avenue (Council Districts 4 & 7).

Body
RECOMMENDATION

Staff recommends the City Council approve a Fourth Amendment to the Consultant Services Agreement, dated January 3, 2019, with Blair, Church, and Flynn Consulting Engineers, Inc., in the amount of $55,400, increasing the total contract amount to $268,179.72, for the Fresno Midtown Trail Project on the north bank of the Mill Ditch along McKinley Avenue from Millbrook Avenue to Clovis Avenue, and authorize the Public Works Director or designee to sign and execute the Fourth Amendment to the Agreement on behalf of the City of Fresno.

EXECUTIVE SUMMARY

The City is proposing to construct a pedestrian and cycle multipurpose trail on the north bank of the Mill Ditch along McKinley Avenue from Millbrook Avenue to Clovis Avenue, which is referred to as Segment 4 of the Midtown Trail Program. The City entered into the Consultant Services Agreement with Blair, Church, and Flynn Consulting Engineers, Inc., for Segment 4 and Segment 5, on January 3, 2019. This Fourth Amendment to the Agreement includes additional design services in order to finalize the construction documents and third party coordination for Segment 4 in preparation for bidding the project. The cost of the Fourth Amendment is $55,400, increasing the total contract amount to $268,179.72 for Segment 4, ...

Click here for full text