Fresno Logo
File #: ID 23-477    Version: 1 Name:
Type: Action Item Status: Passed
File created: 3/14/2023 In control: City Council
On agenda: 3/30/2023 Final action: 3/30/2023
Title: Approve Contract Change Order No. 13 with Avison Construction extending the date of completion to July 6, 2022 for the Clovis Avenue Metro Trail - McKinley to Shields (Midtown Trail Segment 5) Project ID PW00764 (Council District 4)
Sponsors: Public Works Department
Attachments: 1. 23-477 Contract Change Order No. 13
REPORT TO THE CITY COUNCIL


FROM: SCOTT L. MOZIER, PE, Director
Public Works Department

BY: WILLIAM C. HERR, Assistant Director
Public Works Department, Construction Management Division

DAVID A. BOOGAARD, Chief Engineering Inspector
Public Works Department, Construction Management Division

SUBJECT
Title
Approve Contract Change Order No. 13 with Avison Construction extending the date of completion to July 6, 2022 for the Clovis Avenue Metro Trail - McKinley to Shields (Midtown Trail Segment 5) Project ID PW00764 (Council District 4)

Body
RECOMMENDATION

Staff recommends that City Council approve Contract Change Order No. 13 in the amount of $0.00 on behalf of the City of Fresno to Avison Construction to increase Contract Time by twenty-eight (28) working days.

EXECUTIVE SUMMARY

The purpose of the change order is to allow the Contractor twenty-eight (28) additional working days due to the delay with material procurement for the Bollard Style Trail Lights that are identified on the construction drawings to be installed along the Clovis Avenue Metro Trail. The impact of this delay resulted in delaying the Contractor from completing the project and will not increase the Contract amount.

BACKGROUND

On June 10, 2021, a Contract was awarded in the amount of $1,482,760.00 to Avison Construction, for the Clovis Avenue Metro Trail - McKinley to Shields (Midtown Trail Segment 5). The Notice to Proceed was issued with a start date of February 14, 2022, and a Completion Date of May 09, 2022. There have been twelve (12) Contract Change Orders executed to date totaling $74,060.95, resulting in a Revised Contract Price of $1,556,820.95. There have been ten (10) days added to the Contract Time by executed Contract Change Orders and two (2) approved weather days resulting in a Revised Contract Completion Date of May 25, 2022.

The Bollard Style Trail Lights were approved and ordered in early December 2021 and received in late June 2022. The duration of ...