Legislation Details

File #: ID 26-1295    Version: 1 Name:
Type: Action Item Status: Agenda Ready
File created: 9/28/2026 In control: City Council
On agenda: 10/22/2026 Final action:
Title: Approve Amendment No. 1 to the Preliminary Engineering Services Agreement with BNSF Railway Company in the amount of $100,438.80, bringing the total contract to $300,000.00, to perform engineered design plan review and diagnostic evaluation, for the Blackstone Avenue and McKinley Avenue BNSF Grade Separation Project (Council Districts 1 and 7)
Sponsors: Capital Projects Department, Public Works Department
Attachments: 1. 26-1295 Amendment No. 1 to Prelimiary Engineering Services Agreement, 2. 26-1295 Preliminary Engineering Services Agreement, 3. 26-1295 Vicnity Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
REPORT TO THE CITY COUNCIL


FROM: NICHOLAS D. MASCIA, PE, Assistant City Manager
Interim Director, Capital Projects Department

SCOTT MOZIER, PE, Director
Public Works Department

BY: SCOTT P. SEHM, PE, Assistant Director
Capital Projects Department, Design Services Division

ADAM LEE, PE, Licensed Professional Engineer
Capital Projects Department, Design Services Division

SUBJECT
Title
Approve Amendment No. 1 to the Preliminary Engineering Services Agreement with BNSF Railway Company in the amount of $100,438.80, bringing the total contract to $300,000.00, to perform engineered design plan review and diagnostic evaluation, for the Blackstone Avenue and McKinley Avenue BNSF Grade Separation Project (Council Districts 1 and 7)

Body
RECOMMENDATION

Staff recommends the City Council approve Amendment No. 1 to the Preliminary Engineering Services Agreement with BNSF Railway Company for the Blackstone Avenue and McKinley Avenue Grade Separation Project. The Amendment increases the agreement amount by $100,438.80, from $199,561.20 to $300,000. Staff further recommends the City Council authorize the Capital Projects Director, or their designee, to execute the Amendment on behalf of the City of Fresno.

EXECUTIVE SUMMARY

The Blackstone Avenue and McKinley Avenue BNSF Railway Company (BNSF) Grade Separation Project will eliminate two existing at-grade crossings by grade-separating North Blackstone Avenue and East McKinley Avenue under the BNSF mainline track. As the City began presenting design plan elements to BNSF for review and comment, a Preliminary Engineering Services Agreement (PEA) was required for BNSF to formally accept the engineered plan submittals.

On March 2, 2022, the City Council approved the original PEA with BNSF for $199,561.20 and authorized the Public Works Director or designee to execute the agreement. The PEA allowed the City and BNSF to conduct engineering and diagnostic meetings to jointly establish critical design elements, includin...

Click here for full text