REPORT TO THE CITY COUNCIL
FROM: MARK THORPE, Director of Aviation
Airports Department
BY: FRANCISCO PARTIDA, C.M., C.A.E., USAP, Assistant Director of Aviation
Airports Department
CRISTAL DE LA TORRE, Projects Administrator
Airports Department
SUBJECT
Title
Approve a Consultant Services Agreement with Kimley-Horn and Associates, Inc. of Las Vegas, Nevada for the design and preparation of construction documents for the Fresno Chandler Executive Airport Hangar Development Project in the amount of $121,914 with a completion date later than October 8, 2027 (Council District 3)
Body
RECOMMENDATIONS
Staff recommends that Council approve an agreement with Kimley-Horn and Associates, Inc. of Las Vegas, Nevada in the amount of $121,914 for the design and preparation of construction documents for the Fresno Chandler Executive Airport Hangar Development Project (Project) and authorize the Director of Aviation to sign the standardized agreement for consultant services on behalf of the City of Fresno (City).
EXECUTIVE SUMMARY
The City of Fresno Airports Department seeks to enter into an Agreement for Consultant Services with Kimley-Horn and Associates, Inc. in the amount of $121,914 for the design and preparation of construction documents for the Fresno Chandler Executive Airport Hangar Development Project (Project). Pursuant to the Fresno Chandler Executive Airport (FCH) Master Plan 2021 update, the existing T-Hangars west of the terminal have reached the end of their useful life and removal and replacement rather than refurbishment is recommended.
BACKGROUND
In 2021 the Airports Department retained a design consultant to perform a master plan update for Fresno Chandler Executive Airport (FCH). The master plan update is an FAA driven process that identifies the capital needs of FCH based on forecasted air traffic growth for the next 20 years. The process culminates with an FAA approved updated Airport Layout Plan (ALP), which is a key funding tool that ...