Fresno Logo
File #: ID18-0736    Version: 1 Name:
Type: Action Item Status: Agenda Ready
File created: 6/4/2018 In control: City Council
On agenda: 6/21/2018 Final action:
Title: Actions pertaining to the Blackstone Avenue Overlay project, from Shaw Avenue to Ashlan Avenue, Bid File 3561 (Council Districts 4 and 7) 1. Adopt a finding of a Categorical Exemption per staff determination, pursuant to Section 15301(c) of the California Environmental Quality Act Guidelines for the Blackstone Avenue Overlay project, from Shaw Avenue to Ashlan Avenue 2. Award a Construction Contract in the amount of $1,740,296.00 with Cal Valley Construction of Fresno, California, as the lowest responsive and responsible bidder for the Blackstone Avenue Overlay Project from Shaw Avenue to Ashlan Avenue
Sponsors: Public Works Department
Attachments: 1. 18-0736 Bid Evaluation.pdf, 2. 18-0736 Fiscal Impact.pdf, 3. 18-0736 Vicinity Map.pdf, 4. 18-0736 Standardized Contract.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

REPORT TO THE CITY COUNCIL

 

 

 

June 21, 2018

 

 

FROM:                     SCOTT L. MOZIER, PE, Director

Public Works Department

 

BY:                                          RANDALL W. MORRISON, PE, Assistant Director

                                          Public Works Department, Engineering Division

 

                                          M. SCOTT TYLER, PE, Public Works Manager

                                          Public Works Department, Project Management Section

 

                                          TIM GROH, Project Manager

                                          Public Works Department, Project Management Section

 

SUBJECT

Title

Actions pertaining to the Blackstone Avenue Overlay project, from Shaw Avenue to Ashlan Avenue, Bid File 3561 (Council Districts 4 and 7)

1.                     Adopt a finding of a Categorical Exemption per staff determination, pursuant to Section 15301(c) of the California Environmental Quality Act Guidelines for the Blackstone Avenue Overlay project, from Shaw Avenue to Ashlan Avenue

2.                     Award a Construction Contract in the amount of $1,740,296.00 with Cal Valley Construction of Fresno, California, as the lowest responsive and responsible bidder for the Blackstone Avenue Overlay Project from Shaw Avenue to Ashlan Avenue

 

Body

RECOMMENDATION

 

Staff recommends that the City Council adopt a finding of a Categorical Exemption per staff determination, pursuant to Section 15301(c) of the California Environmental Quality Act Guidelines (CEQA), award a construction contract with Cal Valley Construction of Fresno, California in the amount of $1,740,296.00 as the lowest responsive and responsible bidder for the Blackstone Avenue Overlay project, from Shaw Avenue to Ashlan Avenue and authorize the Public Works Director or designee to sign the standardized contract on behalf of the City.

 

EXECUTIVE SUMMARY

 

The Blackstone Avenue Overlay project, from Shaw Avenue to Ashlan Avenue will rehabilitate the asphalt concrete pavement along that portion of Blackstone Avenue.  The project will also make minor concrete repairs to bring curb ramps up to current Americans with Disabilities Act compliance.  Awarding this construction project to Cal Valley Construction will extend the life of this highly used street. 

 

The low bidder, Dave Christian Construction Co., Inc., submitted a bid of $1,625,713.20; however, it was deemed to be “non-responsive” due to the Contractor failing to meet the Disadvantage Business Enterprise requirements for the project.  Therefore, staff recommends the award of the construction contract to Cal Valley Construction as the lowest responsive and responsible bidder.

 

BACKGROUND

 

The Blackstone Avenue asphalt concrete overlay from Shaw to Ashlan Avenues was initiated in FY14 when the City was awarded a Federal grant from the Regional Surface Transportation Program (RSTP).  The grant funds were obligated and the project was budgeted in the adopted FY15 Capital Budget by City Council.  The design started following the Council approval of the consultant contract with Provost & Pritchard Engineering Group, Inc., on February 16, 2017. The preliminary engineering design took approximately 7 months to complete. There was no Right of Way required for this project.

 

Blackstone Avenue between Shaw Avenue and Ashlan Avenue is a heavily used arterial street that is suffering from pavement deterioration.  The proposed grind and overlay project will extend the service life of the street and bring affected curb ramps up to current Americans with Disabilities Act standards.  The scope of the project includes, but is not limited to, a 0.20' asphalt grind and 0.20’ overlay, pavement section repair, concrete repair and striping. 

 

The Notice Inviting Bids was published in the Business Journal on April 6, 2018, posted on the City’s website and faxed to eleven (11) building exchanges. The specifications were distributed to five (5) prospective bidders.  Three (3) sealed bid proposals were received and opened in a public bid opening on May 8, 2017. Bids ranged from $1,625,713.20 to $2,217,361.00. Dave Christian Construction Inc. submitted the apparent low bid of $1,625,713.20, however it was deemed to be “non-responsive” due to the Contractor failing to meet the Disadvantage Business Enterprise requirements for the project.  As a result, Cal Valley Construction, inc., which submitted a bid in the amount of $1,740,296.00, was determined to be the lowest responsive and responsible bidder for the project.  The bids will expire 64 days after the bid opening, on May 8, 2018.

 

Staff is recommending that the Council award a construction contract with Cal Valley Construction of Fresno in the amount of $1,740,296.00 for the Blackstone Avenue Overlay project, from Shaw Avenue to Ashlan Avenue and authorize the Public Works Director or designee to sign and execute the standardized contract on behalf of the City of Fresno.

 

ENVIRONMENTAL FINDINGS

 

Staff performed a preliminary environmental assessment of this project and has determined that it falls within the Categorical Exemption set forth in CEQA Guidelines, Section 15301 (c) Class 1 which exempts the repair and maintenance of existing facilities that involves negligible or no expansion of an existing use.  This exemption applies because this project involves the resurfacing of an existing roadway and does not involve the expansion of the roadway to accommodate additional traffic.  The purpose of the project is to increase the life of the pavement and provide a smooth riding surface for the motorists.  Furthermore, staff has determined that none of the exceptions to Categorical Exemptions set forth in the CEQA Guidelines, Section 15300.2 apply to this project.

 

LOCAL PREFERENCE

 

The local preference was not implemented based on conditions of the Federal RSTP grant.

 

FISCAL IMPACT

 

The Blackstone Avenue AC Overlay from Shaw to Ashlan Avenues is located in Council Districts 4 and 7. The overall cost of the project is $2,220,863.80 and is primarily funded by Federal RSTP, and SB1 Gas Tax will be the local match. The SB1 funding for the project is available in the City’s existing accounts and was included in the FY2018 list of projects for SB1 revenues, as adopted by the Council. The project will have no impact to the General Fund.  All funds necessary for the contract award are included in this fiscal years approved City of Fresno budget.  Of the overall budget for the project, $1,740,296.00 will be used for the construction contract award.

 

 

Attachments:                     

Bid Evaluation

Fiscal Impact

Vicinity Map

Standardized Contract