Skip to main content
Fresno Logo
File #: ID 25-957    Version: 1 Name:
Type: Action Item Status: Agenda Ready
File created: 6/26/2025 In control: City Council
On agenda: 7/17/2025 Final action:
Title: Approve Contract Change Order No. 11 in the amount of $301,686.91, with no additional working days for the Overrun of Bid Item Quantities, the repair of pumping subgrade areas, and the addition of two residential traffic circles with Cal Valley Construction, Inc. of Fresno, California for City of Fresno Paving Bid Package at Various Locations Project - Project ID SM00050. (Bid File 12402606) (Council Districts - 1, 3, 4, 5, 6 and 7)
Sponsors: Capital Projects Department, Public Works Department
Attachments: 1. 25-957 Construction Contract-Cal Valley Construction, Inc. .pdf, 2. 25-957 Contract Change Order No. 1.pdf, 3. 25-957 Contract Change Order No. 2.pdf, 4. 25-957 Contract Change Order No. 3.pdf, 5. 25-957 Contract Change Order No. 4.pdf, 6. 25-957 Contract Change Order No. 5.pdf, 7. 25-957 Contract Change Order No. 6.pdf, 8. 25-957 Contract Change Order No. 7.pdf, 9. 25-957 Contract Change Order No. 8.pdf, 10. 25-957 Contract Change Order No. 9.pdf, 11. 25-957 Contract Change Order No. 10.pdf, 12. 25-957 Contract Change Order No. 11.pdf, 13. 25-957 Vicinity Map.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

REPORT TO THE CITY COUNCIL

 

FROM:                     NICHOLAS D. MASCIA, PE, Assistant City Manager

Office of Mayor & City Manager

 

DENIX ANBIAH, Capital Projects Director

Capital Projects Department

 

SCOTT L. MOZIER, PE, Director

Public Works Department

 

BY:                                          JOSHUA S. RHODES, PE, Assistant Director

                                          Capital Projects Department, Construction Management Division

 

KELLY YOST, PE, Construction Manager

                                          Capital Projects Department, Construction Management Division

 

SUBJECT

Title

Approve Contract Change Order No. 11 in the amount of $301,686.91, with no additional working days for the Overrun of Bid Item Quantities, the repair of pumping subgrade areas, and the addition of two residential traffic circles with Cal Valley Construction, Inc. of Fresno, California for City of Fresno Paving Bid Package at Various Locations Project - Project ID SM00050. (Bid File 12402606) (Council Districts - 1, 3, 4, 5, 6 and 7)

 

Body

RECOMMENDATION

 

Staff recommends that the City Council approve Contract Change Order No. 11 with Cal Valley Construction Inc. of Fresno, California which increases the contract amount by $301,686.91, for a revised contract total of $8,704,811.91, with no additional working days for the Overrun of Bid Item Quantities, the repair of pumping subgrade areas, and the addition of two residential traffic circles for the City of Fresno Paving Bid Package at Various Locations project and authorize the Capital Projects Department Director, or designee, to sign this Contract Change Order No. 11 on behalf of the City of Fresno.

 

EXECUTIVE SUMMARY

 

On June 27, 2024, a contract was awarded in the amount of $7,358,665.00 to Cal Valley Construction, Inc. of Fresno, California for street paving, concrete repair, and ADA improvements in eight (8) separate project areas. These projects are similar in scope and were combined into one single bid package project to provide economy of scale and streamline the process of bidding and awarding the contract. City Council Approval of Contract Change Order No. 11 in the amount of $301,686.91, with no additional working days, is necessary to compensate Cal Valley Construction, Inc. for Bid Item overruns in striping, utility adjustments, concrete sidewalk, curb and gutter, HMA Paving, repair of pumping subgrades, and the addition of two residential traffic circles. Approval of this proposed Contract Change Order will allow the project to move forward and provide compensation to cover the additional quantities and work required to complete this project.  This increase will result in a revised contract total of $8,704,811.91, which is still 27.7% below the original Engineer’s Estimate of $12,048,426.63.  This project is funded through a combination of SB1 Gas Tax, Measure C, and American Rescue Plan Act (ARPA) funding, which are included in the FY2024 budget adopted by Council.

 

BACKGROUND

 

On June 27, 2024, a contract was awarded in the amount of $7,358,665.00 to Cal Valley Construction, Inc. for the City of Fresno Paving Bid Package at Various Locations Project. The project includes 8 separate project areas as follows: the streets within the Dakota-Shields-First-Fresno neighborhood, Fruit Avenue between Clinton and Dakota, the streets within the Ceasar Chavez-Maple-Huntington-Chestnut neighborhood, the streets within the Shields-Crystal-Clinton-Hughes neighborhood, the streets within the Browning-Bullard-Millbrook-Ninth neighborhood, First Street from Sierra to Herndon and Echo Avenue from Olive to McKinley. The scope of work within the Rialto-Marks-Norwich-Valentine neighborhood includes concrete repair and street paving. The Notice to Proceed was issued with a start date of October 14, 2024, and a contract completion date of July 31, 2025.

 

There have been ten (10) prior Contract Change Orders approved totaling $1,044,460.00, resulting in a revised contract total of $8,403,125.00. There have been zero (0) days added to the contract time by the previously executed Contract Change Orders, with fourteen (14) weather days and no suspension days, resulting in a revised contract completion date of August 20, 2025.


During grinding and paving operations in Area 2 and Area 4, areas of existing pumping subgrade were uncovered during grinding operations. This Contract Change Order compensates the Contractor for the additional work to remove the saturated subgrade materials and replace them with suitable materials so that paving could be completed.

 

The Contract Change Order also provides compensation to the Contractor for various Bid Item Overruns in striping, utility adjustments, concrete sidewalk, curb and gutter, HMA Paving, and the addition of two residential traffic circles as requested by the Public Works Department.

 

City Council approval of Contract Change Order No. 11 for an additional $301,686.91 is required by Resolution 2017-158, which sets the approval thresholds for individual Contract Change Orders which exceed 1% of the total contract price or $100,000.00 or aggregate Contract Orders that exceed 10% of the original Contract amount.  The amount of Contract Change Order No. 11 is $301,686.91, which when combined with previously approved change orders, is an aggregate total of 18.3% of the original Contract amount. This increase will result in a revised contract total of $8,704,811.91. There will be no working days added to the contract time by this Contract Change Order, no working days added by previous Contract Change Orders, 14 weather days, and no Suspension days resulting in a revised Contract Completion date of August 20, 2025. 

 

This contract is covered by the Community Workforce Agreement (or Project Labor Agreement, PLA), adopted by the Council in September 2021. The Contractor for this project has become signatory to the PLA by executing the Agreement To Be Bound.

 

Staff recommends that the City Council authorize the Capital Projects Department Director, or designee, to sign Contract Change Order No.11 for the City of Fresno Paving Bid Package Various Locations Project on behalf of the City.

 

ENVIRONMENTAL FINDINGS

 

On June 27, 2024, the Council adopted a finding of Categorical Exemption pursuant to Sections 15301/Class 1, 15302/Class 2, and 15303/Class 4 of the California Environmental Quality Act (CEQA) Guidelines. Based on staff analysis, it was determined that no adverse environmental impacts would occur because of the proposed project and none of the exceptions to Categorical Exemptions set forth in the CEQA Guidelines Section 15300.2 apply to this project.

 

LOCAL PREFERENCE

 

Local preference is not applicable for this project due to it being funded by State SB1 Gas Tax and ARPA which precludes local preference.

 

FISCAL IMPACT

 

The City of Fresno Paving Bid Package Various Locations project area are within Council Districts 1, 3, 4, 5, 6, and 7. The project is funded through a combination of SB1 Gas Tax, Measure C - Street Maintenance, and ARPA funding, which are included in the FY2024 budget adopted by Council. This Change Order will have no impact on the General Fund. The project remains within the construction contingency for the project that was included in the adopted FY2025 budget for the Public Works Department.

 

Attachments:

 

Construction Contract - Cal Valley Construction, Inc.

Contract Change Order No. 1

Contract Change Order No. 2

Contract Change Order No. 3

Contract Change Order No. 4

Contract Change Order No. 5

Contract Change Order No. 6

Contract Change Order No. 7

Contract Change Order No. 8

Contract Change Order No. 9

Contract Change Order No. 10

Contract Change Order No. 11

Vicinity Map