File #: ID 24-730    Version: 1 Name:
Type: Action Item Status: Passed
File created: 5/15/2024 In control: City Council
On agenda: 6/6/2024 Final action: 6/6/2024
Title: Approve a Consultant Services Agreement with O'Dell Engineering Inc, of Fresno, California in the amount of $298,476, with a contingency amount not to exceed $40,000, for design and construction support services for the Dickey Park Rehabilitation Project (Council District 3).
Sponsors: Capital Projects Department, Parks, After School, Recreation and Community Serv
Attachments: 1. 24-730 Consultant Agreement.pdf, 2. 24-730 Vicinity Map.pdf, 3. 24-730 Location Map.pdf

REPORT TO THE CITY COUNCIL

 

 

FROM:                     Randall W. Morrison, PE, Director

                                          Capital Projects Department

 

AARON A. AGUIRRE, Director

Parks, After School, Recreation, and Community Services Department

 

BY:                                          francisco V. magos II, PE, Assistant Director

                                          Capital Projects Department, Utilities and On-Site Project Management Division

 

                                          HARLAVPREET S. BRAR, PE, Licensed Professional Engineer

                                          Capital Projects Department, Utilities and On-Site Project Management Division

 

SUBJECT

Title

Approve a Consultant Services Agreement with O’Dell Engineering Inc, of Fresno, California in the amount of $298,476, with a contingency amount not to exceed $40,000, for design and construction support services for the Dickey Park Rehabilitation Project (Council District 3).

 

Body

RECOMMENDATION

 

Staff recommends City Council approve a Consultant Services Agreement with O’Dell Engineering Inc, of Fresno, California in the amount of $298,476, with a contingency amount not to exceed $40,000, for the design and preparation of construction documents for the Dickey Park Rehabilitation Project (Project) and authorize the Capital Projects Director or designee to execute the agreement on behalf of the City.

 

EXECUTIVE SUMMARY

 

The City of Fresno Parks, After School, Recreation, and Community Services Department (PARCS) proposes to revitalize Dickey Park (Park) by designing and constructing improvements deemed necessary to renovate and enhance the overall recreation experience at the Park. The Project will further develop a schematic conceptual plan created through a community engagement process held in 2022 and 2023.

 

The consultant services agreement for professional architectural and engineering services will be funded using Fiscal Year (FY) 2024 Measure P, Expenditure Category 1-Highest Needs appropriations. Council approval of the consultant services agreement between the City and O’Dell Engineering Inc. (O’Dell) is recommended to facilitate community engagement and the development of plans, cost estimates, and general construction contract documents necessary to complete the Project.

 

BACKGROUND

 

Dickey Park is located on the northwest corner of Blackstone Avenue and Divisadero Street. The PARCS Department proposes to utilize Measure P, Expenditure Category 1-Highest Needs Funding to revitalize the existing facilities and enhance the guest experience at the Park. In 2022, after a competitive procurement process, PARCS selected WRT to develop the initial conceptual plans for the Park. After several community engagement opportunities, the initial conceptual plan was designed.

 

Using the conceptual plan as a basis of design, PARCS intends to advance the Project by proceeding with the preparation of the construction documents under the terms of this consultant services agreement with O’Dell. As part of the Project, O’Dell will analyze the existing site conditions, conduct one community outreach meeting, and develop final construction documents. Subject to funding availability and community engagement, the Project may include a plaza space, restroom, multi-use field, resurfaced basketball court, relocated volleyball courts, an entry plaza, and security fencing, among other features.

 

In accordance with AO 6-19, staff sent out a request for Statement of Qualifications (SOQs) in January 2024 via Planet Bids, email, and published in The Business Journal for the Dickey Park Rehabilitation Project. Four (4) SOQs were received, and staff interviewed the three (3) qualified respondents between March 5, 2024, and March 8, 2024. O’Dell was determined to be the most qualified and responsive based on the consultant interviews. Staff negotiated a fee of $298,476, with a contingency amount not to exceed $40,000, for the design and preparation of construction documents, specifications, cost estimates, community outreach, bidding support services, and construction support services for this Project.

 

Staff recommends City Council approve the proposed agreement with O’Dell Engineering Inc. in the amount of $298,476, with a contingency amount not to exceed $40,000, for the design and preparation of construction documents for the Dickey Park Rehabilitation Project and authorize the Capital Projects Director or designee to sign on behalf of the City.

 

The City Attorney’s Office has reviewed and approved the proposed agreement as to form.

 

ENVIRONMENTAL FINDINGS

 

A consultant agreement for the design of plans and cost estimates is not a “project” pursuant to California Environmental Quality Act (CEQA) Guidelines § 15378.

 

LOCAL PREFERENCE

 

Local preference was implemented in the consultant selection process pursuant to the Fresno Municipal Code Section 4-109. O’Dell Engineering Inc., is a local business, as defined by the Fresno Municipal Code.

 

FISCAL IMPACT

 

The proposed Project is in Council District 3. The Dickey Park Rehabilitation Project is funded through FY2024 Measure P, Expenditure Category 1-Highest Needs Funds and will have no impact to the General Fund.

 