File #: ID 23-957    Version: 1 Name:
Type: Action Item Status: Passed
File created: 6/7/2023 In control: City Council
On agenda: 6/22/2023 Final action: 6/22/2023
Title: Actions pertaining to the Roof Membrane Replacement at the Fresno-Clovis Regional Wastewater Reclamation Facility Administration Building (Bid File 12302214) (Council District 3): 1. Adopt a finding of Categorical Exemption pursuant to Sections 15301/Class 1 and 15302/Class 2 of the California Environmental Quality Act Guidelines. 2. Award a construction contract, in the amount of $353,233, to Nations Roof West, LLC., of Fresno, California.
Sponsors: Department of Public Utilities
Attachments: 1. Attachment 1 - Notice of Exemption.pdf, 2. Attachment 2 - Environmental Assessment.pdf, 3. Attachment 3 - Bid Evaluation and Fiscal Impact Statement.pdf, 4. Attachment 4 - Sample Contract.pdf, 5. Attachment 4 - Vicinity Map.pdf

REPORT TO THE CITY COUNCIL

 

 

FROM:                     BROCK D. BUCHE, PE, PLS, Director

Department of Public Utilities

 

BY:                     JESUS A. GONZALEZ, PE, Assistant Director

                     Department of Public Utilities - Utilities Planning & Engineering

 

                     SAMUEL NADORES, Professional Engineer

                     Department of Public Utilities - Utilities Planning & Engineering

 

SUBJECT

Title

Actions pertaining to the Roof Membrane Replacement at the Fresno-Clovis Regional Wastewater Reclamation Facility Administration Building (Bid File 12302214) (Council District 3):

1.                     Adopt a finding of Categorical Exemption pursuant to Sections 15301/Class 1 and 15302/Class 2 of the California Environmental Quality Act Guidelines.

2.                     Award a construction contract, in the amount of $353,233, to Nations Roof West, LLC., of Fresno, California.

 

Body

RECOMMENDATION

 

Staff recommends that City Council adopt a finding of Categorical Exemption, pursuant to Sections 15301/Class 1 and 15302/Class 2 of the California Environmental Quality Act (CEQA) Guidelines for the Roof Membrane Replacement at the Fresno-Clovis Regional Wastewater Reclamation Facility (Facility) Administration Building (Project); award a construction contract to Nations Roof West, LLC., (Nations), in the amount of $353,233; and authorize the Director of Public Utilities, or designee, to sign and execute all documents on behalf of the City of Fresno (City).

 

EXECUTIVE SUMMARY

 

The Administration Building at the Facility has experienced recurring water leaks on its roof and needs immediate replacement to prevent further damage. The Department of Public Utilities, Wastewater Management Division (WMD), seeks to award a construction contract to Nations. In accordance with the City’s competitive bidding process, Nations was identified as the lowest responsive and responsible bidder in the amount of $353,233.

 

BACKGROUND

 

Built in 2005, the Facility’s Administration Building has experienced recurring water leaks due to its aged roof. The existing roof is past its serviceable life and needs to be replaced to prevent further damage to the building’s interior.  

 

The Project includes removal of the existing thermoplastic polyolefin roof system, roof insulation and related flashing elements down to the metal deck followed by installation of a new polyvinyl chloride roofing system and insulation with a 20-year manufacturer warranty.

 

Following preparation of Project plans and specifications, a Notice Inviting Bids was published on March 16, 2023, and posted on the City’s Planet Bids website. Specifications were distributed to 15 prospective bidders and posted at 6 Building Exchanges. Three sealed bid proposals were received and publicly opened on April 18, 2023 with the costs ranging from $329,923 to $475,571. The lowest bidder was deemed non-responsive for failing to submit the required documents. Nations was then identified as the lowest, responsive and responsible bidder, with a submitted bid amount of $353,233. The bids will expire on July 21, 2023.

 

Staff recommends the City Council award a construction contract to Nations, in the amount of $353,233, as the lowest responsive and responsible bidder. The funding for this Project is included in the five-year capital improvement budget within the Wastewater Management Division’s Sewer Enterprise Fund 40501. The City Attorney has reviewed and approved the standard contract as to form. Upon approval by the City Council, the agreement will be executed by the Director of Public Utilities, or his designee.

 

ENVIRONMENTAL FINDINGS

 

Staff performed a preliminary environmental assessment for this Project and determined that it falls within Sections 15301/Class 1 and 15302/Class 2 Categorical Exemptions set forth in the CEQA Guidelines.

 

LOCAL PREFERENCE

 

Local preference was not implemented as the lowest responsive and responsible bidder qualifies as a local business pursuant to Fresno Municipal Code section 4-108(d).

 

FISCAL IMPACT

 

There is no impact to the General Fund.  Funding for this Project is included in the five-year capital improvement budget within the Wastewater Management Division’s Sewer Enterprise Fund 40501. The Project is located in Council District 3. 

 

 

Attachments:

Attachment 1 - Notice of Exemption

Attachment 2 - Environmental Assessment

Attachment 3 - Bid Evaluation and Fiscal Impact Statement

Attachment 4 - Sample Contract

Attachment 5 - Vicinity Map