Legislation Details

File #: ID 26-699    Version: 1 Name:
Type: Action Item Status: Passed
File created: 5/13/2026 In control: City Council
On agenda: 6/4/2026 Final action: 6/4/2026
Title: Actions pertaining to the Replacement of One Makeup Air Unit and Two Air Handling Units in the Headworks Building at the Fresno-Clovis Regional Wastewater Reclamation Facility (Bid File 12601341) (Council District 3) 1. Adopt a finding of Categorical Exemption pursuant to Section 15301/Class 1 (Existing Facilities) and Section 15302/Class 2 (Replacement or Reconstruction) of the California Environmental Quality Act Guidelines, Environmental Assessment No. TC00176-HC003 2. Award a Construction Contract in the amount of $833,658 to Strategic Mechanical Inc., of Fresno, California, as the lowest responsive and responsible bidder
Sponsors: Capital Projects Department, Department of Public Utilities
Attachments: 1. 26-699 Environmental Assessment, 2. 26-699 Bid Evaluation and Fiscal Impact Statement, 3. 26-699 Standardized Construction Contract, 4. 26-699 Vicinity Map, 5. 26-699 Location Map

PREPORT TO THE CITY COUNCIL

 

 

FROM:                     DENIX D. ANBIAH, PE, Director

Capital Projects Department

 

PAUL AMICO, PE, Director

                                          Department of Public Utilities

 

BY:                                          CASSIE L. SCHOLZ, PE, Assistant Director

                                          Capital Projects Department, Utilities Project Management Division

 

                                          CHARLES MASTERS, Engineer II

                                          Capital Projects Department, Utilities Project Management Division

 

SUBJECT

Title

Actions pertaining to the Replacement of One Makeup Air Unit and Two Air Handling Units in the Headworks Building at the Fresno-Clovis Regional Wastewater Reclamation Facility (Bid File 12601341) (Council District 3)

1.                     Adopt a finding of Categorical Exemption pursuant to Section 15301/Class 1 (Existing Facilities) and Section 15302/Class 2 (Replacement or Reconstruction) of the California Environmental Quality Act Guidelines, Environmental Assessment No. TC00176-HC003

2.                     Award a Construction Contract in the amount of $833,658 to Strategic Mechanical Inc., of Fresno, California, as the lowest responsive and responsible bidder

 

Body

RECOMMENDATIONS

 

Staff recommends City Council (1) adopt a finding of Categorical Exemption pursuant to Section 15301/Class 1 (Existing Facilities) and Section 15302/Class 2 (Replacement or Reconstruction) of the California Environmental Quality Act (CEQA) Guidelines, Environmental Assessment No. TC00176-HC003, (2) award a Construction Contract in the amount of $833,658 to Strategic Mechanical Inc., as the lowest responsive and responsible bidder for the Replacement of One Makeup Air Unit and Two Air Handling Units in the Headworks Building at the Fresno-Clovis Regional Wastewater Reclamation Facility (Project), and authorize the Capital Projects Director or designee to sign and execute all documents on behalf of the City of Fresno (City).

 

EXECUTIVE SUMMARY

 

The Project will replace critical ventilation units in the Fresno-Clovis Regional Wastewater Reclamation Facility (RWRF) Headworks Building that are original to its 1993 construction. These units maintain temperature in electrical rooms and control ventilation in the Headworks Building. The scope of work includes removal of existing units, furnishing and installing replacement units, and providing temporary units during construction. The Capital Projects Department seeks to award a Construction Contract to Strategic Mechanical Inc., of Fresno, California, following a competitive bidding process that identified them as the lowest responsive and responsible bidder in the amount of $833,658.  Funding for the Project is included in the Fiscal Year 2026 Capital Improvement Budget within the Wastewater Management Division’s Wastewater Operating Fund.

 

BACKGROUND

 

The first stage of treatment for wastewater at the RWRF occurs in the Headworks Building, which was constructed in 1993. The building houses the initial stages of the wastewater treatment process, and it includes screening, grit removal, and chemical injection before pumping the wastewater into the treatment process. Ventilation and climate control in the building are critical and are provided by four makeup air units (MAU) and two air-handling units (AHU). The units are susceptible to shortened service lives based on the highly corrosive environment in the Headworks. Units MAU-002, AHU-001 and AHU-002 have reached end of life and replacement is necessary.

 

On April 2, 2024, the City entered into an Agreement with Pcubed Associates Inc. to provide engineering design services for an amount not to exceed $143,195. The scope of services included the design of replacement units in compliance with current development codes.

 

Upon completion of the design, the Project was advertised for construction. A Notice Inviting Bids was advertised and published on the City’s website and Planet Bids on March 24, 2026. The Project plans and specifications were distributed to 15 prospective bidders and posted at three (3) Building Exchanges. Two (2) sealed bid proposals were received and publicly opened on April 28, 2026, with bids ranging from $833,658 to $1,025,000, with Strategic Mechanical Inc. established as the lowest responsive and responsible bidder in the amount of $833,658. The bids are set to expire on July 1, 2026.

 

Staff now recommends City Council adopt a finding of Categorical Exemption pursuant to Section 15301/Class 1 (Existing Facilities) and Section 15302/Class 2 (Replacement or Reconstruction) of the CEQA Guidelines, Environmental Assessment No. TC00176-HC003, approve a Construction Contract in the amount of $833,658 to Strategic Mechanical Inc. as the lowest responsive and responsible bidder for the Project, and authorize the Capital Projects Director or designee to sign and execute all documents on behalf of the City of Fresno (City).

 

The City Attorney’s Office has reviewed and approved the Standardized Construction Contract as to form.

 

ENVIRONMENTAL FINDINGS

 

Staff has reviewed the scope and nature of this Project and determined that it is categorically exempt from the requirements of CEQA pursuant to Section 15301/Class 1 (Existing Facilities) and Section 15302/Class 2 (Replacement or Reconstruction) of the CEQA Guidelines. These exemptions apply because the improvements to the Project serve the existing purpose of the facility, and do not provide any expansion of existing use. The Project does not have the potential to have an adverse effect on the environment and will be compliant with CEQA §15300.2.

 

LOCAL PREFERENCE

 

Strategic Mechanical Inc. of Fresno, California is a local business, as defined by the Fresno Municipal Code.

 

FISCAL IMPACT

 

The Project is in Council District 3 and has no impact on the General Fund. Funding is included in the Fiscal Year 2026 Capital Improvement Budget within the Wastewater Management Division’s Wastewater Operating Fund.

 

Attachments:

Environmental Assessment

Bid Evaluation and Fiscal Impact Statement

Standardized Construction Contract

Vicinity Map

Location Map