Title: Actions pertaining to the Department of Transportation Fresno Area Express Replace HVAC FAX Administration Building Project, Project ID: FC00036 1. Approve Contract Change Order No. 4 to Strategic Mechanical, Inc. in the amount of $93,898.43 2. Approve Contract Change Order No. 5 to Strategic Mechanical, Inc. in the amount of $1,644.74
Sponsors: Public Works Department, Department of Transportation
Attachments: 1. 23-595 Contract Change Order No. 4, 2. 23-595 Contract Change Order No. 5

REPORT TO THE CITY COUNCIL

 

 

FROM:                     SCOTT L. MOZIER, PE, Director

Public Works Department

 

GREGORY A. BARFIELD, M.A., Interim Director

Department of Transportation

 

BY:                                          WILLIAM C. HERR, Assistant Director

                                          Public Works Department, Construction Management Division

 

 

SUBJECT

Title

Actions pertaining to the Department of Transportation Fresno Area Express Replace HVAC FAX Administration Building Project, Project ID: FC00036

1.                     Approve Contract Change Order No. 4 to Strategic Mechanical, Inc. in the amount of $93,898.43

2.                     Approve Contract Change Order No. 5 to Strategic Mechanical, Inc. in the amount of $1,644.74

 

Body

RECOMMENDATION

 

Staff recommends Council approve Contract Change Order No. 4 in the amount of $93,898.43 for the replacement of two (2) HVAC air handlers, and Contract Change Order No. 5 in the amount of $1,644.74 for the replacement of four (4) failed duct fire dampers in the existing HVAC ductwork.

 

EXECUTIVE SUMMARY

 

Item 1. Contract Change Order No. 4 provides for the replacement of two (2) of the existing air handlers.  This equipment and associated work was not identified in the original contract documents and replacement is necessary to make the system fully functional. 

 

Item 2. Contract Change Order No. 5 provides for the replacement of duct fire damper equipment that has failed.  As a requirement of the Unform Building & Safety Codes, testing was performed on the existing HVAC ductwork and the fire dampers incorporated inside of the ductwork.  The results of this testing indicated that four (4) of the existing dampers failed to operate as designed and will require full replacement of these units to comply with current codes.

 

BACKGROUND

 

On September 30, 2021, Council awarded a construction contract in the amount of $549,994.92 to Strategic Mechanical, Inc. for the Replacement of the HVAC System at the FAX Administration Building. The Notice to Proceed was issued with a start date of April 20, 2022, and completion date of October 16, 2022. There have been three (3) Contract Change Orders approved to date totaling $12,649.15, resulting in a revised Contract Price of $656,542.50. There have also been sixty two (62) suspension days granted to allow for the hot weather temperatures to pass prior to switching out HVAC equipment resulting in a revised Contract Completion Date of December 18, 2022. The original scope was determined to be substantially complete on December 18, 2022, and ready for its intended use.

 

During construction it was discovered that the existing air handlers were in need of extensive repairs and had outlived their functional life expectancy and the most cost effective remedy is the replacement of this equipment.  This work was not identified in the original contract documents.

 

The Building Code required testing was performed on the existing HVAC ductwork and the fire dampers incorporated inside of the ductwork.  It was determined that four (4) of the existing dampers failed to operate as designed and will require removal and replacement of these units to comply with current Code.  This work was also not identified in the original contract documents.

 

ENVIRONMENTAL FINDINGS

 

Staff has reviewed the scope and nature of this Project and through Environmental Assessment P21-04668 determined that the scope of this Project falls under Section 15301/Class 1 and Section 15303/Class 3 Categorial Exemptions set for the California Environmental Quality Act (CEQA) Guidelines, as this Project is for the replacement of existing HVAC systems involving negligible or no expansion of capacity.  The project will replace existing HVAC systems at the FAX Administration Building to meet current standards. Furthermore, none of the exceptions to Categorical Exemptions set forth in the CEQA Guidelines, Section 15300.2 apply to this project. This project is not expected to have a significant effect on the environment.

 

LOCAL PREFERENCE

 

Local preference was not implemented as this is a change to an existing award.

 

FISCAL IMPACT

 

This project has no fiscal impact to the General Fund.  This project will be funded from State of California Proposition 1B State of Good Repairs funds and FTA 5307/5339 grants.

 

 

Attachment(s):

Contract Change Order No. 4 

Contract Change Order No. 5