File #: ID 25-654    Version: 1 Name:
Type: Action Item Status: Agenda Ready
File created: 5/5/2025 In control: City Council
On agenda: 5/22/2025 Final action:
Title: Reject all bids received for the purchase of four (4) Allen-Bradley PF755TL 800 HP ND Type 1 Variable Frequency Drives for the Fresno-Clovis Regional Wastewater Reclamation Facility. (Bid File 12502008) (Council District 3)
Sponsors: Department of Public Utilities
Attachments: 1. 25-654 Bid Evaluation and Fiscal Impact Statement, 2. 25-654 Vicinity Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

REPORT TO THE CITY COUNCIL

 

 

FROM:                     BROCK D. BUCHE, PE, PLS, Director

                                          Department of Public Utilities

 

BY:                                          CASSIE L. SCHOLZ, PE, Licensed Engineer Manager

                                          Department of Public Utilities - Utilities Planning & Engineering

 

                                          JOSHUA MERTEN, Engineer I

                                          Department of Public Utilities - Utilities Planning & Engineering

 

SUBJECT

Title

Reject all bids received for the purchase of four (4) Allen-Bradley PF755TL 800 HP ND Type 1 Variable Frequency Drives for the Fresno-Clovis Regional Wastewater Reclamation Facility. (Bid File 12502008) (Council District 3)

 

Body

RECOMMENDATIONS

 

Staff recommends that City Council reject all bids received for the purchase of four (4) Allen-Bradley PF755TL 800 HP ND Type 1 Variable Frequency Drives for the Fresno-Clovis Regional Wastewater Reclamation Facility (RWRF).

 

EXECUTIVE SUMMARY

 

The existing raw sewage pump variable frequency drives (VFDs) at the RWRF are no longer reliable and the Department of Public Utilities is seeking to replace them. The sole bidder on the Product Purchase Contract took exception to the terms and conditions of the bid specifications and has been deemed non-responsive.

 

Within 90 days, the staff will pursue the purchase of four (4) Allen-Bradley PF755TL 800 HP ND Type 1 Variable Frequency Drives with an approved method of procurement.

 

BACKGROUND

 

The VFDs are used at the RWRF to control raw sewage pump motors to accommodate the varying wastewater flows into the facility. The current VFDs were retrofitted in 2013 and have been reliable until 2019 at which time the facility has experienced failures at rate of two VFDs per year. This project will replace the existing VFDs with a 6-pulse technology that will be much more robust, reliable, and supported for years to come.

 

The Notice Inviting Bids was published on Planet Bids on March 25, 2025. One bid was received and opened at the public bid opening on April 15, 2025. The bidder took exceptions to the specifications and has been deemed non-responsive.

 

Staff will pursue the purchase of four (4) Allen-Bradley PF755TL 800 HP ND Type 1 Variable Frequency Drives with an approved method of procurement within 90 days.

 

 

ENVIRONMENTAL FINDINGS

 

By the definition of the California Environmental Quality Act (CEQA) Guidelines Section 15378, the approval of this item does not qualify as a “project” for the purpose of CEQA.

 

LOCAL PREFERENCE

 

Local preference is not applicable because this action is to reject all bids.

 

FISCAL IMPACT

 

There is no impact on the General Fund. This item is for the rejection of all received bids.

 