Title: Approve the First Amendment to the Professional Engineering Services Agreement with Michael K. Nunley & Associates, Inc., of Fresno, California, in the amount of $12,710, increasing the total contract amount to $624,379, with a remaining contingency amount not to exceed $6,647, due to an increased scope of services for the construction document phase of the Southwest Recycled Water System Storage Tank and Booster Pump Station Project (Fresno County).
Sponsors: Capital Projects Department, Department of Public Utilities
Attachments: 1. 24-1304 First Amendment to the Agreement.pdf, 2. 24-1304 Original Consultant Agreement.pdf, 3. 24-1304 Vicinity Map.pdf, 4. 24-1304 Location Map.pdf
REPORT TO THE CITY COUNCIL


FROM: RANDALL W. MORRISON, PE, Director
Capital Projects Department

BROCK D. BUCHE, PE, PLS, Director
Department of Public Utilities

BY: FRANCISCO V. MAGOS II, PE, Assistant Director
Capital Projects Department, Utilities and On-Site Project Management Division

PATRICIA DIEP, Project Manager
Capital Projects Department, Utilities and On-Site Project Management Division

SUBJECT
Title
Approve the First Amendment to the Professional Engineering Services Agreement with Michael K. Nunley & Associates, Inc., of Fresno, California, in the amount of $12,710, increasing the total contract amount to $624,379, with a remaining contingency amount not to exceed $6,647, due to an increased scope of services for the construction document phase of the Southwest Recycled Water System Storage Tank and Booster Pump Station Project (Fresno County).

Body
RECOMMENDATION

Staff recommends City Council approve the First Amendment to the Professional Engineering Services Agreement with Michael K. Nunley & Associates, Inc., (MKN) of Fresno, California, in the amount of $12,710, increasing the total contract amount to $624,379, with a remaining contingency amount not to exceed $6,647, due to an increased scope of services for the Southwest Recycled Water System Storage Tank and Booster Pump Station Project (Project) and authorize the Capital Projects Director or designee to sign and execute the First Amendment on behalf of the City of Fresno (City).

EXECUTIVE SUMMARY

The Department of Public Utilities (DPU) has contracted with MKN to design a new recycled water storage tank, booster pump station, and all associated appurtenances at 3315 West Franklin Avenue. The site improvements will ensure adequate pressure for the City's recycled water system and continued service reliability for recycled water delivery. Additionally, these improvements will allow for future expansion to reach those wishing to make use of recycled water. The First Ame...