Title: Approve Contract Change Order No. 3 in the amount of $2,804.25 with forty-four (44) additional working days for the installation of one (1) solar power irrigation controller, cost credit for omitting the removal of pole bases and the installation of a power feed for the existing streetlights, bringing the new Construction Contract total to $7,037,639.37 with $509,224.26 remaining in contingency, with Yarbs Grading and Paving, Inc. of Fowler CA for the MLK Center Active Transportation Infrastructure project located on Martin Luther King Jr. Boulevard between Church Avenue and Jensen Avenue – Project ID PW00842 (Council District 3)
Sponsors: Capital Projects Department, Public Works Department
Attachments: 1. 26-1394 Contract Change Order No. 3, 2. 26-1394 Contract Change Order No. 2, 3. 26-1394 Contract Change Order No.1, 4. 26-1394 Executed Construction Contract - Yarbs Grading and Paving Inc., 5. 26-1394 Vicinity Map, 6. 26-1394 Environmental Assessment No. P21-06568
REPORT TO THE CITY COUNCIL


FROM: NICHOLAS D. MASCIA, PE, Assistant City Manager
Interim-Director, Capital Projects Department

BRIAN RUSSELL, Director
Public Works Department

BY: JASON STARNES, PE, Assistant Director
Capital Projects Department, Construction Management Division

JASON MILLER, PE, Licensed Professional Engineer
Capital Projects Department, Design Services Division

SUBJECT
Title
Approve Contract Change Order No. 3 in the amount of $2,804.25 with forty-four (44) additional working days for the installation of one (1) solar power irrigation controller, cost credit for omitting the removal of pole bases and the installation of a power feed for the existing streetlights, bringing the new Construction Contract total to $7,037,639.37 with $509,224.26 remaining in contingency, with Yarbs Grading and Paving, Inc. of Fowler CA for the MLK Center Active Transportation Infrastructure project located on Martin Luther King Jr. Boulevard between Church Avenue and Jensen Avenue – Project ID PW00842 (Council District 3)

Body
RECOMMENDATION

Staff recommends that the City Council approve Contract Change Order No. 3 (CCO No.3) with Yarbs Grading and Paving, Inc. (Contractor) of Fowler CA, which increases the construction contract (contract) amount by $2,804.25 for a revised contract total of $7,037,639.37 with $509,224.26 remaining in contingency, provides forty-four (44) additional working days to allow for the installation of one solar powered irrigation controller, a cost credit for chipping foundations in lieu of complete removal and the addition of one (1) power feed for the existing streetlights for the MLK Center Active Transportation Infrastructure project, and authorize the City Manager or Designee to sign CCO No.3 on behalf of the City of Fresno.

EXECUTIVE SUMMARY

On September 12, 2024, the City Council awarded a contract in the amount of $6,860,785.12 to Yarbs Grading and Paving, Inc. of Fowler California for the construction of the MLK Ce...