REPORT TO THE CITY COUNCIL
FROM: DENIX D. ANBIAH, PE, Director
Capital Projects Department
BY: FRANCISCO V. MAGOS II, PE, Assistant Director
Capital Projects Department, Utilities and On-Site Project Management Division
DANIEL CARRION, PE, Licensed Professional Engineer
Capital Projects Department, Utilities and On-Site Project Management Division
SUBJECT
Title
Approve Design-Build Contract Amendment No. 1 to the Progressive Design-Build Agreement with Bomel Construction Company Inc. of Irvine, California to increase the design fee by an amount not to exceed $341,890.00, for a total revised contract value not to exceed $1,954,659.00, and increase contingency by an amount not to exceed $35,000.00, for a total revised contingency amount not to exceed $195,000.00 for the North Fulton Parking Structure Project. (Council District 3)
Body
RECOMMENDATIONS
Staff recommends the City Council approve Design-Build Contract Amendment No. 1 to the Progressive Design-Build Agreement with Bomel Construction Company Inc. to increase the design fee by an amount not to exceed $341,890.00, for a total revised contract value not to exceed $1,954,659.00, and increase contingency by an amount not to exceed $35,000.00, for a total revised contingency amount not to exceed $195,000.00 for the North Fulton Parking Structure Project (Project), and authorize the Capital Projects Director or designee to sign Design-Build Contract Amendment No. 1 on behalf of the City of Fresno (City).
EXECUTIVE SUMMARY
In June 2025, Council approved Phase One of a Progressive Design-Build Agreement with Bomel Construction Company Inc. to provide design services for the North Fulton Parking Structure Project located on the southern half of APN 466-206-50T & 51T along Merced Street. The approved contract included the design of a parking structure containing 234 parking stalls, intended to supply residential parking for future Infill Infrastructure Grant Catalytic (IIGC) housing deve...
Click here for full text