File #: ID 25-1120    Version: 1 Name:
Type: Action Item Status: Agenda Ready
File created: 8/8/2025 In control: Pending Approval
On agenda: 8/28/2025 Final action:
Title: Approve Design-Build Contract Amendment No. 1 to the Progressive Design-Build Agreement with Bomel Construction Company Inc. of Irvine, California to increase the design fee by an amount not to exceed $341,890.00, for a total revised contract value not to exceed $1,954,659.00, and increase contingency by an amount not to exceed $35,000.00, for a total revised contingency amount not to exceed $195,000.00 for the North Fulton Parking Structure Project. (Council District 3)
Sponsors: Capital Projects Department
Attachments: 1. 25-1120 Amendment No. 1 to Progressive Design-Build Contract, 2. 25-1120 Original Design-Build Contract.pdf, 3. 25-1120 Vicinity Map.pdf, 4. 25-1120 Location Map.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
REPORT TO THE CITY COUNCIL


FROM: DENIX D. ANBIAH, PE, Director
Capital Projects Department

BY: FRANCISCO V. MAGOS II, PE, Assistant Director
Capital Projects Department, Utilities and On-Site Project Management Division

DANIEL CARRION, PE, Licensed Professional Engineer
Capital Projects Department, Utilities and On-Site Project Management Division

SUBJECT
Title
Approve Design-Build Contract Amendment No. 1 to the Progressive Design-Build Agreement with Bomel Construction Company Inc. of Irvine, California to increase the design fee by an amount not to exceed $341,890.00, for a total revised contract value not to exceed $1,954,659.00, and increase contingency by an amount not to exceed $35,000.00, for a total revised contingency amount not to exceed $195,000.00 for the North Fulton Parking Structure Project. (Council District 3)

Body
RECOMMENDATIONS

Staff recommends the City Council approve Design-Build Contract Amendment No. 1 to the Progressive Design-Build Agreement with Bomel Construction Company Inc. to increase the design fee by an amount not to exceed $341,890.00, for a total revised contract value not to exceed $1,954,659.00, and increase contingency by an amount not to exceed $35,000.00, for a total revised contingency amount not to exceed $195,000.00 for the North Fulton Parking Structure Project (Project), and authorize the Capital Projects Director or designee to sign Design-Build Contract Amendment No. 1 on behalf of the City of Fresno (City).

EXECUTIVE SUMMARY

In June 2025, Council approved Phase One of a Progressive Design-Build Agreement with Bomel Construction Company Inc. to provide design services for the North Fulton Parking Structure Project located on the southern half of APN 466-206-50T & 51T along Merced Street. The approved contract included the design of a parking structure containing 234 parking stalls, intended to supply residential parking for future Infill Infrastructure Grant Catalytic (IIGC) housing deve...

Click here for full text