REPORT TO THE CITY COUNCIL
June 25, 2015
FROM: THOMAS C. ESQUEDA, Director
Department of Public Utilities
BY: MICHAEL CARBAJAL, Division Manager
Department of Public Utilities - Water Division
SUBJECT
Title
Approve the acquisition of a permanent easement for APN 580-020-21, and a permanent easement and temporary construction easement for APN 580-020-23, from: George G. Goshgarian & Kathleen A. Gregory (who acquired title as Kathleen A. Goshgarian) (undivided 1/32 interest); Michael Morales (undivided 3/32 interest); Leonard Verni (undivided 1/4 interest) & Nicholas Verni (undivided 1/4 interest); Steven G. Fogg Family Partnership, A California Partnership (undivided 1/8 interest); Steven G. Fogg Family Partnership, A California Limited Partnership (undivided 1/8 interest); Christopher T. Lum, Sole Trustee of the Steven C.Y. Lum and Catherine J. Lum Trust (undivided 1/8 interest).
Body
RECOMMENDATIONS
Staff recommends that City Council:
1. Approve the acquisition of a permanent easement and temporary construction easement as shown in the attached Table for the construction of the Raw Water Pipeline from the Friant-Kern Canal to the Northeast Surface Water Treatment Facility (NESWTF).
2. Authorize the Director of Public Utilities, or his designee, to sign all documents on behalf of the City.
EXECUTIVE SUMMARY
The Department of Public Utilities, Water Division, is finalizing the design of the Friant Kern Raw Water Pipeline to deliver raw water from the Friant-Kern Canal to the NESWTF. With bidding scheduled to begin in summer 2015, acquisition of easements for this pipeline project is necessary. The following property owners have agreed to the compensation of $29,600 for the acquisition of a permanent easement, and $120/year for the acquisition of a temporary construction easement (see attachment Table 1): George G. Goshgarian & Kathleen A. Gregory (who acquired title as Kathleen A. Goshgarian) (undivided 1/32 in...
Click here for full text