REPORT TO THE CITY COUNCIL
FROM: DENIX D. ANBIAH, PE, Director
Capital Projects Department
BY: FRANCISCO V. MAGOS II, PE, Assistant Director
Capital Projects Department, Utilities and On-Site Project Management Division
ROBERT A. DIAZ, Project Manager
Capital Projects Department, Utilities and On-Site Project Management Division
SUBJECT
Title
Actions pertaining to the Infill Infrastructure Grant Catalytic Downtown Water and Sewer Improvements Project (Bid File 12600298) (Council District 3):
1. Adopt an Initial Study - Mitigated Negative Declaration as prepared for SCH 2025100590 dated October 14, 2025, for the Infill Infrastructure Grant Catalytic Downtown Water and Sewer Improvements Project pursuant to the California Environmental Quality Act Guidelines;
2. ***RESOLUTION - Adopting the 23rd Amendment to the Annual Appropriation Resolution No. 2025-179 appropriating $2,770,200.00 for the Infill Infrastructure Grant Catalytic Downtown Water and Sewer Improvements Project (Requires 5 Affirmative Votes) (Subject to Mayor's Veto);
3. Award a construction contract in the amount of $23,550,277.49, for the Base Bid plus all four (4) Add Alternates, to Katch Environmental, Inc. dba Katch General of Fresno, California as the lowest responsive and responsible bidder for the Infill Infrastructure Grant Catalytic Downtown Water and Sewer Improvements Project.
Body
RECOMMENDATIONS
Staff recommends City Council (1) adopt an Initial Study - Mitigated Negative Declaration (IS-MND) as prepared for SCH 2025100590 dated October 14, 2025 for the Infill Infrastructure Grant Catalytic (IIGC) Downtown Water and Sewer Improvements Project (Project) pursuant to the California Environmental Quality Act (CEQA) Guidelines, (2) adopt the 23rd Amendment to the Annual Appropriation Resolution (AAR) 2025-179 appropriating $2,770,200.00 for the IIGC Downtown Water and Sewer Improvements Project, (3) award a construction contract in the amount of $23,550,277.49 for the B...
Click here for full text