REPORT TO THE CITY COUNCIL
FROM: DENIX D. ANBIAH, PE, Director
Capital Projects Department
JENNIFER K. CLARK, AICP, Director
Planning and Development Department
BY: FRANCISCO V. MAGOS II, PE, Assistant Director
Capital Projects Department, On-Site Project Management Division
KELLY YOST, PE, Construction Manager
Capital Projects Department, Construction Management Division
SUBJECT
Title
Approve Contract Change Order No. 03 with Katch Environmental Incorporated dba Katch General of Fresno, California in the amount of $83,886.57 increasing the total contract amount to $3,892,302.81 with 26 additional working days for the Garage 9 Renovation Project. (Bid File 12500982) (Council District 3)
Body
RECOMMENDATION
Staff recommends that City Council approve Contract Change Order No. 03 with Katch Environmental Incorporated dba Katch General of Fresno, California in the amount of $83,886.57 with twenty-six (26) additional working days to allow for completion of changes for the Garage 9 Renovation Project (Project), and authorize the Capital Projects Department Director, or designee, to sign this Contract Change Order No. 03 on behalf of the City of Fresno.
EXECUTIVE SUMMARY
On January 09, 2025, a Contract was awarded in the amount of $3,462,279.00 to Katch Environmental Incorporated dba Katch General of Fresno, California for the Garage 9 Renovation Project. Council approved Contract Change Order No. 01 for $203,438.20, raising the contract total to $3,665,717.20. Subsequently, CCO No. 02 was executed for $142,699.04, resulting in a revised contract total of $3,808,416.24.
City Council approval of Contract Change Order No. 03, in the amount of $83,886.57, is recommended to support the continued progress of the Project. This change includes twenty-six (26) additional working days, which will allow for the completion of the necessary improvements and ensure the project remains on track for successful delivery. This increase wi...