File #: ID18-0013    Version: 1 Name:
Type: Action Item Status: Passed
File created: 12/18/2017 In control: City Council
On agenda: 1/11/2018 Final action: 1/11/2018
Title: Actions pertaining to the Design of the Reclaimed Water Pipeline at the Regional Wastewater Reclamation Facility (Council District 3) 1. ***RESOLUTION - 46th Amendment to the Annual Appropriation Resolution No. 2017-165 appropriating $91,000 for Design of the Reclaimed Water Pipeline at the Fresno/Clovis Regional Wastewater Reclamation Facility (Requires 5 affirmative votes) (Subject to Mayor's veto) 2. Award a Professional Consultant Services Agreement in the amount of $70,970 and a contingency of $10,000 to Blair, Church & Flynn, Inc., a California Corporation, for professional engineering services for the Design of the Reclaimed Water Pipeline at the Regional Wastewater Reclamation Facility (Council District 3)
Sponsors: Department of Public Utilities
Attachments: 1. 18 46th Reclaimed Wtr Pipeline WRF SAM.pdf, 2. 2018-01-11 BCF Consultant Agreement.pdf
REPORT TO THE CITY COUNCIL


January 11, 2018


FROM: THOMAS C. ESQUEDA, Director
Department of Public Utilities

THROUGH: MICHAEL CARBAJAL, Planning Manager
Department of Public Utilities - Utilities Planning & Engineering

BY: RAUL GONZALEZ, Professional Engineer
Department of Public Utilities - Utilities Planning & Engineering

SUBJECT
Title

Actions pertaining to the Design of the Reclaimed Water Pipeline at the Regional Wastewater Reclamation Facility (Council District 3)
1. ***RESOLUTION - 46th Amendment to the Annual Appropriation Resolution No. 2017-165 appropriating $91,000 for Design of the Reclaimed Water Pipeline at the Fresno/Clovis Regional Wastewater Reclamation Facility (Requires 5 affirmative votes) (Subject to Mayor's veto)
2. Award a Professional Consultant Services Agreement in the amount of $70,970 and a contingency of $10,000 to Blair, Church & Flynn, Inc., a California Corporation, for professional engineering services for the Design of the Reclaimed Water Pipeline at the Regional Wastewater Reclamation Facility (Council District 3)

Body
RECOMMENDATIONS

Staff recommends the City Council approve the 46th amendment to the Annual Appropriation Resolution No. 2017-165 to appropriate the project funds; award a Professional Consultant Services Agreement in the amount of $70,970 to Blair, Church & Flynn, Inc., a California Corporation, for the design of the Reclaimed Water Pipeline at the Regional Wastewater Reclamation Facility (RWRF); and authorize the Director of Public Utilities or designee to execute the Agreement on behalf of the City of Fresno.

EXECUTIVE SUMMARY

The Department of Public Utilities requests to adopt the 46th Amendment to the Annual Appropriation Resolution No. 2017-165 and award of a Professional Consultant Services Agreement in the amount of $70,970 with a $10,000 contingency to Blair, Church & Flynn, Inc., for the design of the Reclaimed Water Pipeline connecting the existing Houghton Pipeline to the existin...

Click here for full text