File #: ID 26-296    Version: 1 Name:
Type: Action Item Status: Passed
File created: 3/4/2026 In control: City Council
On agenda: 3/26/2026 Final action: 3/26/2026
Title: Approve the substitution of listed Subcontractor, Dawn Electric Inc. of Hanford, California, for electrical work with Strategic Mechanical Inc. of Fresno, California, for the Vinland Park Futsal and Pickleball Courts Project - Project ID PC00351 (Bid File 12500501). (Council District 4)
Sponsors: Capital Projects Department
Attachments: 1. 26-296 Executed Contract, 2. 26-296 Alliance Construction Solutions, Inc., Letter to Request Subcontractor Substitution, 3. 26-296 City of Fresno, Acknowledgement Letter of Substitution Request - Alliance Construction Solutions, Inc., 4. 26-296 City of Fresno, Substitution of Subcontractor Letter - Dawn Electric, Inc., 5. 26-296 USPS Delivery Verification, 6. 26-296 Vicinity Map, 7. 26-296 Location Map
REPORT TO THE CITY COUNCIL


FROM: DENIX D. ANBIAH, PE, Director
Capital Projects Department

BY: ANTONIO M. BUELNA, PE, Assistant Director
Capital Projects Department, Construction Management Division

KELLY YOST, PE, Construction Manager
Capital Projects Department, Construction Management Division

SUBJECT
Title
Approve the substitution of listed Subcontractor, Dawn Electric Inc. of Hanford, California, for electrical work with Strategic Mechanical Inc. of Fresno, California, for the Vinland Park Futsal and Pickleball Courts Project - Project ID PC00351 (Bid File 12500501). (Council District 4)

Body
RECOMMENDATION

Staff recommends the City Council approve the request from Alliance Construction Solutions, Inc. of Madera, California, to substitute Dawn Electric Inc. of Hanford, California and utilize Strategic Mechanical Inc. of Fresno, California for the electrical portions of this project.

EXECUTIVE SUMMARY

On June 12, 2025, a Contract was awarded in the amount of $1,168,921.77 to Alliance Construction Solutions, Inc. for the Vinland Park Futsal and Pickleball Courts Project. Alliance Construction Solutions, Inc. has requested to substitute Dawn Electric Inc., who is listed in the bid documents as performing the electrical portions of the project with Strategic Mechanical Inc. This action requires City Council approval per Public Contract Code Section 4107, whereas the consent of the awarding authority is required to approve a request by a prime contractor for a substitution of a subcontractor.

BACKGROUND

On June 12, 2025, a Contract was awarded in the amount of $1,168,921.77 to Alliance Construction Solutions, Inc, for construction of one (1) futsal court and four (4) pickleball courts within Vinland Park, located at 4695 E Gettysburg Avenue, as well as the installation of additional site amenities including, but not limited to, picnic tables, benches, shade structures and drinking fountains. The Notice to Proceed was issued Februa...

Click here for full text