File #: ID 24-1174    Version: 1 Name:
Type: Action Item Status: Passed
File created: 8/22/2024 In control: City Council
On agenda: 9/12/2024 Final action: 9/12/2024
Title: Approve Amendment No. 3 to Measure "C" Cooperative Project Agreement, Grade Separation Program, for the Blackstone & McKinley BNSF Grade Separation Project, in the amount of $23,380,062, for a total increased agreement amount not to exceed $58,500,000, with the Fresno County Transportation Authority. (Council Districts 1 and 7)
Sponsors: Capital Projects Department, Public Works Department
Attachments: 1. 24-1174 Amendment No. 3 to Cooperative Project Agreement.pdf, 2. 24-1174 Amendment No. 2 to Cooperative Project Agreement.pdf, 3. 24-1174 Amendment No. 1 to Cooperative Project Agreement.pdf, 4. 24-1174 Cooperative Project Agreement.pdf, 5. 24-1174 Vicinity Map.pdf
REPORT TO THE CITY COUNCIL


FROM: RANDALL W. MORRISON, PE, Director
Capital Projects Department

SCOTT L. MOZIER, PE, Director
Public Works Department

BY: AUSTIN M. BAIN, PE, Licensed Professional Engineer
Capital Projects Department, Transportation Project Management Division

SUBJECT
Title
Approve Amendment No. 3 to Measure "C" Cooperative Project Agreement, Grade Separation Program, for the Blackstone & McKinley BNSF Grade Separation Project, in the amount of $23,380,062, for a total increased agreement amount not to exceed $58,500,000, with the Fresno County Transportation Authority. (Council Districts 1 and 7)

Body
RECOMMENDATION

Staff recommends the City Council approve Amendment No. 3 to Measure "C" Cooperative Project Agreement, Grade Separation Program (GSP), for the Blackstone & McKinley BNSF Grade Separation Project, in the amount of $23,380,062, for a total increased agreement amount not to exceed $58,500,000, with the Fresno County Transportation Authority (FCTA), and authorize the Public Works Director or designee to sign the amendment on behalf of the City of Fresno.

EXECUTIVE SUMMARY

The Blackstone & McKinley BNSF Grade Separation Project will eliminate two existing at-grade crossings by grade separating North Blackstone Avenue and East McKinley Avenue under the BNSF Mainline Track. The preliminary engineering phase of the project is in progress, with the 60% design package currently being developed. The right of way phase of the project was started in January 2022 and is currently in the right of way acquisition stage. Public Works Staff, with the support of FCTA, has determined a third amendment to the Measure "C" Cooperative Project Agreement, Grade Separation Program (GSP), for the Blackstone & McKinley BNSF Grade Separation Project, in the amount of $23,380,062, for a total increased agreement amount not to exceed $58,500,000, will be necessary to continue the preliminary engineering and right of way phases. The proje...