REPORT TO THE CITY COUNCIL
FROM: BROCK D. BUCHE, PE, PLS, Director
Department of Public Utilities
BY: CASSIE L. SCHOLZ, PE, Licensed Engineer Manager
Department of Public Utilities - Utilities Planning & Engineering
SARAH AGUILA, Project Manager
Department of Public Utilities - Utilities Planning & Engineering
SUBJECT
Title
Actions pertaining to the 2-Water Booster Pump Station Redundancy Improvements at the Fresno-Clovis Regional Wastewater Reclamation Facility (Bid File 12500873) (Council District 3):
1. Adopt a finding of Categorical Exemption pursuant to Section 15301/Class 1 of the California Environmental Quality Act (CEQA) Guidelines;
2. Award a construction contract to Alliance Construction Solutions, Inc., of Madera, California, in the amount of $1,125,500.00.
Body
RECOMMENDATION
Staff recommends the City Council adopt a finding of Categorical Exemption pursuant to Section 15301/Class 1 of the California Environmental Quality Act (CEQA) Guidelines; award a construction contract to Alliance Construction Solutions, Inc., as the lowest responsive and responsible bidder in the amount of $1,125,500.00 for the 2-Water Booster Pump Station Redundancy Improvements at the Fresno-Clovis Regional Wastewater Reclamation Facility (Project); and authorize the Director of Public Utilities, or designee, to sign and execute all documents on behalf of the City of Fresno (City).
EXECUTIVE SUMMARY
The Fresno-Clovis Regional Wastewater Reclamation Facility (RWRF) relies on untreated non-potable water (2-water) production and conveyance for the functionality of critical equipment. The 2-Water Booster Pump Station Redundancy Improvements (Project) will provide redundancy to protect critical assets at the RWRF and allow staff to perform routine service and maintenance of the pump station components. The Department of Public Utilities, Wastewater Management Division (WMD), is seeking to award the Project to Alliance Construction Solutions, Inc., in the ...