Approve Contract Change Order No. 06 with Avison Construction Inc., in the amount of $0 and an increase in contract time of one hundred seventy-four (174) calendar days for the Rebid Fresno Area Express Bus Entry Gate, Project ID FC00036 (Council District 3).
Body
RECOMMENDATION
Staff recommends that the Council approve Contract Change Order No. 06 with Avison Construction Inc. of Madera, California (Avison) for a total increase in contract time of one hundred seventy-four (174) calendar days for the Rebid Fresno Area Express Bus Entry Gate Project.
EXECUTIVE SUMMARY
Delays related to material and equipment procurement due to ongoing global supply chain issues have resulted in the need to provide additional contract time to the Contractor for the Rebid Fresno Area Express Bus Entry Gate, Project ID FC00036. The proposed contract change order will add one hundred seventy-four (174) calendar days to the contract to account for the material and equipment procurement and to align the current project completion date with the contract time. The proposed change order has no monetary change. The Rebid Fresno Area Express Bus Entry Gate contract is fully funded by State of California Prop. 1B, FTA 5307, FTA 5339 and FTA CRRSAA grants as appropriated in the adopted budget.
BACKGROUND
The Municipal Service Center (MSC) entry gate located at Divisadero and 'G' Street is past its useful life and prone to failure. Moreover, the placement of the gate requires vehicles to stage on the street blocking traffic while waiting to enter the MSC. This project provides modernizations such as a faster and more reliable gate system, additional staging space on the...