File #: ID 22-695    Version: 1 Name:
Type: Action Item Status: Passed
File created: 4/26/2022 In control: City Council
On agenda: 5/12/2022 Final action: 5/12/2022
Title: Approve Contract Change Order No. 02 in the amount of $105,795 and forty-five (45) additional contract working days to Nor- Cal Pump & Well Drilling for the Drill New Production Well at Pump Station 36A project, Project ID WC00016 (Council District 5 and Fresno County)
Sponsors: Public Works Department, Department of Public Utilities
Attachments: 1. 22-695 Contract Change Order No 02
REPORT TO THE CITY COUNCIL


FROM: SCOTT L. MOZIER, PE, Director
Public Works Department

BROCK D. BUCHE, PE, PLS, Interim Director
Department of Public Utilities

BY: WILLIAM C. HERR, Assistant Director
Public Works Department, Facilities and Construction Management Divisions

BRADLEY OBERG, Senior Engineering Inspector
Public Works Department, Construction Management Division

SUBJECT
Title
Approve Contract Change Order No. 02 in the amount of $105,795 and forty-five (45) additional contract working days to Nor- Cal Pump & Well Drilling for the Drill New Production Well at Pump Station 36A project, Project ID WC00016 (Council District 5 and Fresno County)

Body
RECOMMENDATION

Staff recommends that City Council approve Contract Change Order No. 02 with Nor-Cal Pump & Well Drilling Inc. for a total increase in contract amount of $105,795 and forty-five (45) additional contract working days for the Drill New Production Well at Pump Station 36A project. Change Order No. 02 provides additional work for hydraulically pressure jetting this well.

EXECUTIVE SUMMARY

On July 29, 2021, Council awarded a contract in the amount of $537,155 to Nor-Cal Pump & Well Drilling, Inc. for the Drill New Production Well at Pump Station 36A project. Staff recommends that City Council approve Contract Change Order No. 02 for the project, increasing the contract amount by $105,795 and adding forty-five (45) additional contract working days. There has been one Contract Change Order executed to date for a total amount $37,808. This well is producing a low yield of water, and additional work is necessary to try to increase efficiency, productivity and functioning of the well for the Water Division. The change order includes hydraulically pressure-jetting the well with added chemicals. This Change Order provides for all related supporting equipment to hydraulically pressure jet this well.

BACKGROUND

On July 29, 2021, a Contract was awarded in the amount...