REPORT TO THE CITY COUNCIL
FROM: DENIX D. ANBIAH, PE, Director
Capital Projects Department
SCOTT L. MOZIER, PE, Director
Public Works Department
BY: ANTONIO M. BUELNA, PE, Assistant Director
Capital Projects Department, Construction Management Division
KELLY YOST, PE, Construction Manager
Capital Projects Department, Construction Management Division
SUBJECT
Title
Approve Contract Change Order No. 6 in the amount not to exceed $112,478.32, with sixty (60) additional working days, for the installation of one step-up transformer, battery controllers for the irrigation system, installation of six (6) solar lights, regrading a valley gutter, grading and compacting for the monument sign, the relocation of electrical conduits, and the installation of a bubbler, with Avison Construction Company, Inc. of Madera, CA for the Transformative Climate Communities Park at MLK Magnet Core (Les Kimber Park) Project - Project ID PW00857. (Bid File 12302905) (Council District 3)
Body
RECOMMENDATION
Staff recommends that the City Council approve Contract Change Order No. 6 with Avison Construction Co., Inc. of Madera California which increases the contract amount not to exceed $112,478.32, for a revised contract total not to exceed $10,992,895.24, with sixty (60) additional working days to allow for the installation of one (1) step-up transformer, battery controllers for the irrigation system, six (6) solar lights for the play area, regrade and compact one (1) valley gutter, relocate an electrical conduit and install one drain bubbler at the Transformative Climate Communities (TCC) Park at MLK Magnet Core Project (Les Kimber Park) and authorize the Capital Projects Department Director, or designee, to sign this Contract Change Order No. 6 on behalf of the City of Fresno.
EXECUTIVE SUMMARY
On October 19, 2023, a contract was awarded in the amount of $8,646,293.00 to Avison Construction Co., Incorporated of Madera California for the TCC Par...
Click here for full text