REPORT TO THE CITY COUNCIL
FROM: DENIX D. ANBIAH, PE, Director
Capital Projects Department
PAUL AMICO, PE, Director
Department of Public Utilities
BY: CASSIE L. SCHOLZ, PE, Assistant Director
Capital Projects Department, Utilities Project Management Division
ANTHONY AQUINO, Engineer II
Capital Projects Department, Utilities Project Management Division
SUBJECT
Title
Actions pertaining to the First Street between Shields and Princeton Water Main Replacement Project (Bid File 12601230) (Council District 4 & 7):
1. Adopt a finding of Categorical Exemption pursuant to Section 15301/Class 1 (Existing Facilities) and 15302/Class 2 (Replacement or Reconstruction) of the California Environmental Quality Act Guidelines;
2. Award a Construction Contract in the amount of $1,193,060.00 to Walsh Montgomery Construction, Inc., as the lowest responsive and responsible bidder.
Body
RECOMMENDATION
Staff recommends City Council (1) adopt a finding of Categorical Exemption pursuant to Section 15301/Class 1 (Existing Facilities) and 15302/Class 2 (Replacement or Reconstruction), of the California Environmental Quality Act (CEQA) Guidelines, and (2) award a Construction Contract in the amount of $1,193,060.00 to Walsh Montgomery Construction, Inc., as the lowest responsive and responsible bidder for the First Street between Shields and Princeton Water Main Replacement Project (Project), and authorize the Capital Projects Director or designee to sign and execute all documents on behalf of the City of Fresno (City).
EXECUTIVE SUMMARY
The Capital Projects Department seeks to award a water main Construction Contract in the amount $1,193,060.00 to Walsh Montgomery Construction, Inc. following a competitive bidding process which identified them as the lowest responsive and responsible bidder. The scope of work includes replacing aging steel pipe and cast iron pipe (CIP) that has reached the end of its service life, with ductile iron pipe (DIP) and C-900 poly...
Click here for full text