File #: ID#15-877    Version: 1 Name:
Type: Action Item Status: Passed
File created: 9/23/2015 In control: City Council
On agenda: 10/8/2015 Final action: 10/8/2015
Title: Actions pertaining to funding and construction of the Commercial West Ramp Reconstruction project at Fresno Yosemite International Airport (Council District 4) 1. ***RESOLUTION - 7th amendment to the Annual Appropriations Resolution (AAR) No. 2015-104 appropriating $6,041,100 for the Commercial West Ramp Reconstruction project at Fresno Yosemite International Airport (Requires 5 affirmative votes) 2. Award a construction contract to A. Teichert & Son, Inc., dba Teichert Construction, of Sacramento, California, for the Commercial West Ramp Reconstruction project at Fresno Yosemite International Airport in the amount of $10,091,945 (Bid File 3402) 3. Approve a consulting agreement with BSK Associates, of Fresno, California, to provide geotechnical quality assurance testing and inspection services for the Commercial West Ramp Reconstruction project at Fresno Yosemite International Airport in the amount of $297,194
Sponsors: Airports Department
Attachments: 1. 10-08-15 FAT West Ramp 7th Amend AAR.pdf, 2. Bid Evaluation Signed 07-27-15 .pdf, 3. West Ramp Consultant Agreement BSK 09-17-15.pdf, 4. West Ramp Site Map Staff Report 10-08-15.pdf
REPORT TO THE CITY COUNCIL



October 8, 2015


FROM: KEVIN R. MEIKLE, Director of Aviation
Airports Department


SUBJECT
Title

Actions pertaining to funding and construction of the Commercial West Ramp Reconstruction project at Fresno Yosemite International Airport (Council District 4)
1. ***RESOLUTION - 7th amendment to the Annual Appropriations Resolution (AAR) No. 2015-104 appropriating $6,041,100 for the Commercial West Ramp Reconstruction project at Fresno Yosemite International Airport (Requires 5 affirmative votes)
2. Award a construction contract to A. Teichert & Son, Inc., dba Teichert Construction, of Sacramento, California, for the Commercial West Ramp Reconstruction project at Fresno Yosemite International Airport in the amount of $10,091,945 (Bid File 3402)
3. Approve a consulting agreement with BSK Associates, of Fresno, California, to provide geotechnical quality assurance testing and inspection services for the Commercial West Ramp Reconstruction project at Fresno Yosemite International Airport in the amount of $297,194

Body
RECOMMENDATIONS

In matters pertaining to the Commercial West Ramp Reconstruction project (Project) at Fresno Yosemite International Airport (FAT), staff recommends that Council: 1) Adopt the 7th Amendment to the AAR No. 2015-104 appropriating $6,041,100 for the Project, 2) Award a construction contract to A. Teichert & Son, Inc., dba Teichert Construction, of Sacramento, California, in the amount of $10,091,945 (Bid File 3402), and, 3) Approve a consulting agreement with BSK Associates of Fresno, California, to provide geotechnical quality assurance (QA) testing and inspection services in the amount of $297,194.

EXECUTIVE SUMMARY

The Pavement Management Plan (PMP) for FAT, as required by the Federal Aviation Administration (FAA), concluded that rehabilitation/reconstruction of the commercial aviation ramp ("apron") on the west side of the terminal is necessary. The Project will remove and r...