Fresno Logo
File #: ID#15-508    Version: 1 Name:
Type: Action Item Status: Passed
File created: 6/3/2015 In control: City Council
On agenda: 6/25/2015 Final action: 6/25/2015
Title: Approve the Common Use Agreement between the Garfield Water District and the City of Fresno for selected parcels where easements for construction, operation and maintenance of the Friant-Kern Canal Raw Water Pipeline will share areas of common use
Sponsors: Department of Public Utilities
Attachments: 1. Common Use Agreement.pdf
REPORT TO THE CITY COUNCIL


June 25, 2015



FROM: THOMAS C. ESQUEDA, Director
Department of Public Utilities

BY: MICHAEL CARBAJAL, Division Manager
Department of Public Utilities - Water Division

SUBJECT
Title
Approve the Common Use Agreement between the Garfield Water District and the City of Fresno for selected parcels where easements for construction, operation and maintenance of the Friant-Kern Canal Raw Water Pipeline will share areas of common use

Body
RECOMMENDATIONS

Staff recommends that City Council:
1. Approve the Common Use Agreement (CUA) between the Garfield Water District (GWD) and the City where easements for construction, operation and maintenance of the Friant-Kern Canal Raw Water Pipeline will share areas of common use with the GWD, as shown in Exhibit A.
2. Authorize the Director of Public Utilities, or his designee, to sign all documents on behalf of the City.

EXECUTIVE SUMMARY

The Department of Public Utilities, Water Division, is finalizing the design of the Friant-Kern Canal Raw Water Pipeline to deliver raw water from the Friant-Kern Canal to the Northeast Surface Water Treatment Facility (NESWTF). With bidding scheduled to begin in summer 2015, establishment of a CUA between the GWD and the City of Fresno (City) for this pipeline project is necessary.

BACKGROUND

Presently, the City's contract with the United States Bureau of Reclamation (USBR) for Central Valley Project (CVP) surface water travels nearly 55 miles in open canals from Friant Dam (Millerton Lake) to the NESWTF. The proposed project consists of the construction and operation of a 5.6-mile raw water pipeline. The new pipeline reroutes the CVP water directly to the NESWTF and will eliminate nearly 47 miles from the conveyance distance. The project will convey water in an enclosed system and greatly reduce the threat to water quality, in otherwise open canals which are exposed to contamination from environmental debris, and ac...

Click here for full text