REPORT TO THE CITY COUNCIL
FROM: SCOTT L. MOZIER, PE, Director
Public Works Department
BY: WILLIAM C. HERR, Assistant Director
Public Works Department, Construction Management Division
DARDEN P. ROCHE, Chief Engineering Inspector
Public Works Department, Construction Management Division
SUBJECT
Title
Approve Contract Change Order No. 03 in the amount of an estimated $174,390.40 for increases in unit cost amounts to Dave Christian Construction Co., Inc. for the North Abby Street HMA Pavement Overlay from Divisadero Street to Olive Avenue, Project ID PW00784 (Bid File 3785) (Council District 3).
Body
RECOMMENDATION
Staff recommends that the City Council approve Contract Change Order No. 03 with Dave Christian Construction Co., Inc for a total estimated increase in Contract Amount of $174,390.40 for the completion of the project for the North Abby Street HMA Pavement Overlay from Divisadero Street to Olive Avenue.
EXECUTIVE SUMMARY
On June 10, 2021, a Contract was awarded in the amount of $879,984.00 to Dave Christian Construction Co., Inc. for the North Abby Street HMA Pavement Overlay from Divisadero Street to Olive Ave. City Council Approval of Contract Change Order No. 03 will allow for an additional estimated $174,390.40 to increase multiple unit cost amounts due to price increases in labor, material, equipment and fuel. The repaving had been delayed for two years due to delays on the PG&E Rule 20 Utility Undergrounding District occurring in the same area. The project was originally fully funded with Federal Regional Surface Transportation Program (RSTP) funds. The funding for the contract change order to pay for increased labor, material, equipment and fuel costs was included in the Senate Bill 1 projects list for FY2024 as previously adopted by the Council.
BACKGROUND
On June 10, 2021, a Contract was awarded in the amount of $879,984.00 to Dave Christian Construction Co., Inc. for the North Abby Street HMA Pavement Overlay from D...