File #: ID 25-1034    Version: 1 Name:
Type: Action Item Status: Agenda Ready
File created: 7/23/2025 In control: City Council
On agenda: 8/14/2025 Final action:
Title: Approve Contract Change Order No. 5 in the amount of $122,470.55, with fifty-eight (58) additional working days for additional improvements to Les Kimber Park for the installation of one monument sign, the redesign at the intersection of West Creek Village and Church Avenue, storm drain adjustments on the west side of the project, the installation of one four-inch water service and the installation of shotcrete at the play area with Avison Construction Company, Incorporated of Madera, California for the Transformative Climate Communities Park at MLK Magnet Core Project - Project ID PW00857. (Bid File 12302905) (Council District 3)
Sponsors: Capital Projects Department, Public Works Department
Attachments: 1. 25-1034 Contract-Avison Construction.pdf, 2. 25-1034 Contract Change Order No. 1.pdf, 3. 25-1034 Contract Change Order No. 2.pdf, 4. 25-1034 Contract Change Order No. 3.pdf, 5. 25-1034 Contract Change Order No. 4.pdf, 6. 25-1034 Contract Change Order No. 5.pdf, 7. 25-1034 Vicinity Map.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
REPORT TO THE CITY COUNCIL

FROM: DENIX D. ANBIAH, PE, Director
Capital Projects Department

SCOTT L. MOZIER, PE, Director
Public Works Department

BY: ANTONIO M. BUELNA, PE, Assistant Director
Capital Projects Department, Administration Division

KELLY YOST, PE, Construction Manager
Capital Projects Department, Construction Management Division

SUBJECT
Title
Approve Contract Change Order No. 5 in the amount of $122,470.55, with fifty-eight (58) additional working days for additional improvements to Les Kimber Park for the installation of one monument sign, the redesign at the intersection of West Creek Village and Church Avenue, storm drain adjustments on the west side of the project, the installation of one four-inch water service and the installation of shotcrete at the play area with Avison Construction Company, Incorporated of Madera, California for the Transformative Climate Communities Park at MLK Magnet Core Project - Project ID PW00857. (Bid File 12302905) (Council District 3)

Body
RECOMMENDATION

Staff recommends that the City Council approve Contract Change Order No. 5 with Avison Construction Co., Incorporated of Madera, California which increases the contract amount by $122,470.55, for a revised contract total of $10,880,416.92, with fifty-eight (58) additional working days to allow for the installation of one monument sign, the redesign at the intersection of West Creek Village and Church Avenue, storm drain adjustments on the west side of the project, the installation of one four-inch water service and the installation of shotcrete at the play area for the Transformative Climate Communities (TCC) Park at MLK Magnet Core project and authorize the Capital Projects Department Director, or designee, to sign this Contract Change Order No. 5 on behalf of the City of Fresno.

EXECUTIVE SUMMARY

On October 19, 2023, a contract was awarded in the amount of $8,646,293.00 to Avison Construction Co., Incorporated of Madera, Califo...

Click here for full text