Title: Approve Amendment to City Hall Solar Power Purchase Agreement (PPA) to adjust the construction schedule and project completion date to provide additional time as requested by Fresno Street Solar Project, LLC.
Sponsors: Public Works Department
Attachments: 1. 21-154 Amendment to the PPA
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
REPORT TO THE CITY COUNCIL


January 28, 2021


FROM: SCOTT MOZIER, Director
Public Works Department

BY: ANN D. KLOOSE, Sustainability Division Manager
Public Works Department


SUBJECT
Title
Approve Amendment to City Hall Solar Power Purchase Agreement (PPA) to adjust the construction schedule and project completion date to provide additional time as requested by Fresno Street Solar Project, LLC.

Body
RECOMMENDATION

Staff recommends Council authorize the Director of Public Works to sign the requested amendment to provide the additional time requested to complete the solar carport project(s) currently underway in the City Hall and Promenade parking lots.

EXECUTIVE SUMMARY

The Public Works Department has been working to implement the City Hall and Municipal Service Center (MSC) energy efficiency and solar projects during the past year. The MSC solar project(s) are completed and the City Hall solar projects are underway. Due to unforeseen delays associated with COVID-19, project design and permitting, the City Hall and Promenade lots will require additional time to complete, and as such require an amendment to the dates of completion in the Power Purchase Agreement (PPA).

BACKGROUND

In November of 2019 the City Council authorized the City Manager to enter into a Design Build Agreement with Alliance Building Solutions (ABS), Inc. for an Energy Performance Contract which included PPAs for solar with subcontractor DSD Renewables. The project(s) at the MSC and City Hall included both upgrades to existing solar, and installs new solar carports. The energy efficiency upgrades are near complete and the solar upgrades and installation at the MSC are concluded. Due to unforeseen delays associated with COVID-19, project design and permitting, the City Hall and Promenade lots will require additional time to complete. The City and DSD Renewables have been coordinating and in mutual agreement regarding the need for additional time. During this time...