File #: ID 26-592    Version: 1 Name:
Type: Action Item Status: Passed
File created: 4/30/2026 In control: City Council
On agenda: 5/21/2026 Final action: 5/21/2026
Title: Actions pertaining to the H Street Parking Structure Project (Council District 3) 1. Adopt a finding that the project is categorically exempt from the requirements of the California Environmental Quality Act (CEQA), pursuant to Class 32/Section 15332 of the CEQA Guidelines, and that none of the exceptions to exemptions set forth in Section 15300.2 apply 2. Approve Design-Build Contract Amendment No. 2 for Phase Two of a Progressive Design-Build Agreement with Bomel Construction Company Inc. of Irvine, California, to provide design and construction services related to the H Street Parking Structure Project in an amount not to exceed $45,123,776.00, bringing the total contract amount to $47,516,755.00
Sponsors: Capital Projects Department
Attachments: 1. 26-592 Categorical Exemption with Technical Studies, 2. 26-592 Design-Build Contract Amendment No. 2, 3. 26-592 Design-Build Contract Amendment No.1, 4. 26-592 Original Design-Build Contract, 5. 26-592 Location Map, 6. 26-592 Vicinity Map
REPORT TO THE CITY COUNCIL


FROM: DENIX D. ANBIAH, PE, Director
Capital Projects Department

BY: FRANCISCO V. MAGOS II, PE, Assistant Director
Capital Projects Department, On-Site Project Management Division

KIMBERLY ALVARADO VEGA, Engineer II
Capital Projects Department, On-Site Project Management Division

SUBJECT
Title
Actions pertaining to the H Street Parking Structure Project (Council District 3)
1. Adopt a finding that the project is categorically exempt from the requirements of the California Environmental Quality Act (CEQA), pursuant to Class 32/Section 15332 of the CEQA Guidelines, and that none of the exceptions to exemptions set forth in Section 15300.2 apply
2. Approve Design-Build Contract Amendment No. 2 for Phase Two of a Progressive Design-Build Agreement with Bomel Construction Company Inc. of Irvine, California, to provide design and construction services related to the H Street Parking Structure Project in an amount not to exceed $45,123,776.00, bringing the total contract amount to $47,516,755.00

Body
RECOMMENDATION

Staff recommends the City Council (1) adopt a finding that the project is categorically exempt from the requirements of the California Environmental Quality Act (CEQA), pursuant to Class 32/Section 15332 of the CEQA Guidelines, and that none of the exceptions to exemptions set forth in Section 15300.2 apply; and (2) approve Design-Build Contract Amendment No. 2 for Phase Two of a Progressive Design-Build Agreement with Bomel Construction Company Inc. to provide design and construction services related to the H Street Parking Structure Project (Project) for an amount not to exceed $45,123,776.00, bringing the total contract amount to $47,516,755.00, and authorize the Capital Projects Director or designee to sign a final Contract on behalf of the City of Fresno.

EXECUTIVE SUMMARY

The Capital Projects Department (CPD) and Mayor's Office have initiated and completed Phase One of the Project, which included schemat...

Click here for full text