Legislation Details

File #: ID 26-995    Version: 1 Name:
Type: Action Item Status: Agenda Ready
File created: 7/15/2026 In control: City Council
On agenda: 7/30/2026 Final action:
Title: Actions pertaining to Phase Two Construction of the Progressive Design-Build as part of the New Terminal Expansion project at Fresno Yosemite International Airport (Council District 4) 1. Approve Change Order No. 2 for Phase Two Construction of the Progressive Design-Build contract with Q&D Construction as part of the New Terminal Expansion project at Fresno Yosemite International Airport for 72 calendar days 2. Approve Change Order No. 3 for Phase Two Construction of the Progressive Design-Build Contract with Q&D Construction as part of the New Terminal Expansion project at Fresno Yosemite International Airport in an amount not to exceed $3,955,687.00 and 90 calendar days
Sponsors: Airports Department
Attachments: 1. 26-995 Site Map, 2. 26-995 Project Change Order 16, 3. 26-995 Independent Construction Estimate - G1 Service
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
REPORT TO THE CITY COUNCIL


FROM: MARK THORPE, Director of Aviation
Airports Department

BY: FRANCISCO PARTIDA, Assistant Director of Aviation
Airports Department

JARRED S. GARZA, Airports Project Manager
Airports Department

SUBJECT
Title
Actions pertaining to Phase Two Construction of the Progressive Design-Build as part of the New Terminal Expansion project at Fresno Yosemite International Airport (Council District 4)
1. Approve Change Order No. 2 for Phase Two Construction of the Progressive Design-Build contract with Q&D Construction as part of the New Terminal Expansion project at Fresno Yosemite International Airport for 72 calendar days
2. Approve Change Order No. 3 for Phase Two Construction of the Progressive Design-Build Contract with Q&D Construction as part of the New Terminal Expansion project at Fresno Yosemite International Airport in an amount not to exceed $3,955,687.00 and 90 calendar days

Body
RECOMMENDATION

Staff recommends that Council 1) approve Contract Change Order No. 2 and grant 72 calendar days for rephasing; 2) approve Contract Change Order No. 3 to increase the Owner Contingency amount for $3,955,687.00 and 90 calendar days for the G1 service elevator scope for the Terminal Expansion Project (Project) at Fresno Yosemite International Airport (FAT) and authorize the Director of Aviation, or designee, to execute all documents related to these change orders.

EXECUTIVE SUMMARY

On February 23, 2023, Council awarded the Phase 2 Construction of the Progressive Design-Build Contract with Q&D Construction for the New Terminal Expansion project at FAT. This construction phase consists of site excavation and grading, underground utilities, approximately 96,000 sq ft terminal building, two passenger boarding bridges, and parking lot improvements. On December 4, 2024, City Council approved Contract Change Order No. 1 for $2,506,006 and 140 calendar days, covering the expanded FIS Arrivals Hall and Plaza.

During the course of construc...