Title: Approve an agreement to reimburse Baltara Enterprises, Limited Partnership an amount not to exceed $63,283 for the design and construction of an 8-inch diameter water main in Santa Fe Street, between Inyo Street and Mono Street and authorize the Director of Public Utilities or designee to sign on behalf of the City (Council District 3).
Sponsors: Department of Public Utilities
Attachments: 1. Water Infrastructure Reimbursement Agreement.pdf
REPORT TO THE CITY COUNCIL


September 24, 2015


FROM: THOMAS C. ESQUEDA, Director
Department of Public Utilities

THROUGH: MICHAEL CARBAJAL, Division Manager
Department of Public Utilities - Water Division

BY: ROBERT A. DIAZ, Senior Engineering Technician
Department of Public Utilities - Water Division

SUBJECT
Title

Approve an agreement to reimburse Baltara Enterprises, Limited Partnership an amount not to exceed $63,283 for the design and construction of an 8-inch diameter water main in Santa Fe Street, between Inyo Street and Mono Street and authorize the Director of Public Utilities or designee to sign on behalf of the City (Council District 3).

Body
RECOMMENDATION

Staff recommends that the City Council approve an agreement to reimburse Baltara Enterprises, Limited Partnership, $63,283 for the design and construction of an 8-inch water main within Conditional Use Permit C-09-166 "Warehouse Row" frontage, replacing an inadequate 6-inch water main for the City of Fresno.

EXECUTIVE SUMMARY

Baltara Enterprises developed property located on the southwesterly corner of the intersection of Santa Fe Street and Inyo Street pursuant to Conditional Use Permit C-09-166. As part of the development, Baltara Enterprises was required to construct an 8-inch water main (including installation of City fire hydrants) in Santa Fe Street to replace an existing 6-inch water main. In 2015, Baltara Enterprises constructed the required water main and it was accepted by the City on August 4, 2015. The attached reimbursement agreement will reimburse Baltara Enterprises $63,283 which is 68% of the cost to construct the replacement water main, plus 11.6% for cost of design and construction administration.

BACKGROUND

Baltara Enterpises developed property, pursuant to Conditional Use Permit C-09-166, located on the southwesterly corner of the intersection of Santa Fe Street and Inyo Street. When the project was proposed in 2014, the...