File #: ID 23-596    Version: 1 Name:
Type: Action Item Status: Passed
File created: 4/6/2023 In control: City Council
On agenda: 4/27/2023 Final action: 4/27/2023
Title: ***RESOLUTION - Adopting the 34th amendment to the Annual Appropriations Resolution (AAR) No. 2022-154 appropriating $1,761,500 for the Parks and Public Safety Energy Efficiency Projects (Citywide) (Requires 5 Affirmative Votes)(Subject to Mayor's Veto)
Sponsors: Public Works Department
Attachments: 1. 23-596 34th Amendment to the AAR 2022-154
REPORT TO THE CITY COUNCIL


FROM: SCOTT L. MOZIER, PE, Director
Public Works Department

BY: WILLIAM C. HERR, Assistant Director
Public Works Department, Construction Management Division

ANN D. KLOOSE, Sustainability Division Manager
Public Works Department, Sustainability Division

SUBJECT
Title
***RESOLUTION - Adopting the 34th amendment to the Annual Appropriations Resolution (AAR) No. 2022-154 appropriating $1,761,500 for the Parks and Public Safety Energy Efficiency Projects (Citywide) (Requires 5 Affirmative Votes)(Subject to Mayor's Veto)

Body
RECOMMENDATION

Staff recommends Council approve the 34th amendment to the Annual Appropriations Resolution (AAR) No. 2022-154 appropriating $1,761,500 in PG&E On-Bill Financing (OBF) 0% interest funding for completion of the Citywide Parks and Public Safety Energy Efficiency Projects.

EXECUTIVE SUMMARY

On February 10, 2022, the Council awarded a Contract in the amount of $17,947,480.00 to Alliance Building Solutions to perform energy efficiency upgrades at 73 project sites throughout the City and authorized staff to execute the project financing. The project, which uniquely pays for itself by utilizing energy bill savings, was partially funded with energy loan financing of $16,247,480.00 at a 2.62% interest rate, with the $1,761,500 balance of the project being funded with revenue from the PG&E 0% interest On-Bill Financing (OBF) program. The estimated interest savings by utilizing the 0% interest was $367,000. This amendment to the AAR is consistent with the original project financing as adopted by the Council, and Council action is now required in order to appropriate the OBF revenue for the project as previously planned.

BACKGROUND

On February 10, 2022, the Council awarded a Contract for the amount of $17,947,480.00 to Alliance Building Solutions to perform energy efficiency upgrades at 73 project sites throughout the City to include interior and exterior LED lighting upgrades, HVAC upgrade...

Click here for full text