File #: ID 25-1351    Version: 1 Name:
Type: Action Item Status: Agenda Ready
File created: 10/1/2025 In control: City Council
On agenda: 10/16/2025 Final action:
Title: Approve Contract Change Order No. 1 in the amount of $136,415.00, with no additional working days for work required outside of the original scope on Cesar Chavez Blvd with Cal Valley Construction, of Fresno, California for the City of Fresno Pave Now - Bid Package A Project - Project ID CP00017. (Bid File 12600087) (Council Districts 1, 2, 3, 4, 5, 6, and 7)
Sponsors: Capital Projects Department, Public Works Department
Attachments: 1. 25-1351 Construction Contract-Cal Valley Construction.pdf, 2. 25-1351 Contract Change Order No. 1.pdf, 3. 25-1351 Vicinity Map.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
REPORT TO THE CITY COUNCIL


FROM: DENIX D. ANBIAH, PE, Director
Capital Projects Department

SCOTT L. MOZIER, PE, Director
Public Works Department

BY: ANTONIO M. BUELNA, PE, Assistant Director
Capital Projects Department, Construction Management Division

KELLY YOST, PE, Construction Manager
Capital Projects Department, Construction Management Division

SUBJECT
Title
Approve Contract Change Order No. 1 in the amount of $136,415.00, with no additional working days for work required outside of the original scope on Cesar Chavez Blvd with Cal Valley Construction, of Fresno, California for the City of Fresno Pave Now - Bid Package A Project - Project ID CP00017. (Bid File 12600087) (Council Districts 1, 2, 3, 4, 5, 6, and 7)

Body
RECOMMENDATION

Staff recommends that the City Council approve Contract Change Order No. 1 with Cal Valley Construction, of Fresno, California which increases the contract amount by $136,415.00, for a revised contract total of $5,859,614.00, for work required outside of the original scope on Cesar Chavez Blvd but deemed necessary to avoid cutting into a newly paved roadway, and authorize the Capital Projects Department Director, or designee, to sign this Contract Change Order No. 1 on behalf of the City of Fresno.

EXECUTIVE SUMMARY

On August 28, 2025, a contract was awarded in the amount of $5,723,199.00 with Cal Valley Construction, of Fresno, California to rehabilitate the pavement in seven (7) separate project areas, which include segments of Shields Avenue, Shaw Avenue, a portion of the McKinley-Palm-Olive-Fruit neighborhood, McKinley Avenue, Cesar Chavez Boulevard, First Street, and portions of Los Angeles, Cherry and Fulton Street near Downtown Fresno. Restorative pavement work will include grind and overlay of the asphaltic concrete roadway to extend the service life of the pavement. Other work includes replacement of roadway striping to match existing, installation of advance stop bars and ...