REPORT TO THE CITY COUNCIL
FROM: NICHOLAS D. MASCIA, PE, Assistant City Manager
Interim Director-Capital Projects Department
SCOTT L. MOZIER, PE, Director
Public Works Department
BY: JOSHUA S. RHODES, PE, Assistant Director
Capital Projects Department, Construction Management Division
KELLY YOST, PE, Construction Manager
Capital Projects Department, Construction Management Division
SUBJECT
Title
Approve Contract Change Order No. 7 in the amount of $89,220.27, with no additional working days for balancing of Contract Bid Item overruns and underruns with Emmett's Excavation, Incorporated of Clovis, California for the Blackstone Avenue and McKinley Avenue Transit Oriented Development Sidewalk and Lighting Project - Project ID PW00926. (Bid File 12300361-12691) (Council Districts 1 and 7)
Body
RECOMMENDATION
Staff recommends that the City Council approve Contract Change Order No. 7 with Emmett's Excavation, Inc., of Clovis, California which increases the contract amount by $89,220.27, for a revised contract total of $2,987,907.75, with no additional working days for balancing of Contract Bid Item overruns and underruns for the Blackstone Avenue and McKinley Avenue Transit Oriented Development Project and authorize the Capital Projects Department Director, or designee, to sign this Contract Change Order No. 7 on the City's behalf.
EXECUTIVE SUMMARY
On June 22, 2023 a contract was awarded in the amount of $2,649,222.00 to Emmett's Excavation, Inc, of Clovis, California for the Blackstone Avenue and McKinley Avenue Transit Oriented Development Sidewalk and Lighting Project to provide improvements to pedestrian accessibility along Blackstone Avenue by constructing missing sidewalk segments, ADA-compliant commercial drive approaches, water infrastructure improvements, upgrading street lighting, and installing pedestrian-scale lighting between Hedges Avenue and Cambridge Avenue. City Council Approval of Contract Change Order No. 7...