REPORT TO THE CITY COUNCIL
FROM: DENIX D. ANBIAH, PE, Director
Capital Projects Department
SCOTT L. MOZIER, PE, Director
Public Works Department
BY: ANTONIO BUELNA, PE, Assistant Director
Capital Projects Department, Interim Construction Management Division
KELLY YOST, PE, Construction Manager
Capital Projects Department, Construction Management Division
SUBJECT
Title
Approve Contract Change Order No. 04 in the amount of $92,731.92, with no additional working days for overruns of various bid item quantities, additional roadway excavation for areas not included in the original contract, and the addition of sod to restore homeowners' disturbed lawns with Avison Construction, Inc. of Madera, California for the Muir Elementary Safe Routes Project - Project ID PW00893. (Bid File 12301163-12561) (Council District 3)
Body
RECOMMENDATION
Staff recommends that the City Council approve Contract Change Order No. 4 with Avison Construction, Inc. of Madera, California which increases the contract amount by $92,731.92, for a revised contract total of $1,910,730.96, with no additional working days for overruns of various bid item quantities, additional roadway excavation for areas not included in the original contract, and the addition of sod to restore homeowners' disturbed lawns for the Muir Elementary Safe Routes Project and authorize the Capital Projects Department Director, or designee, to sign this Contract Change Order No. 4 on behalf of the City of Fresno.
EXECUTIVE SUMMARY
On May 25, 2023, a contract was awarded in the amount of $1,695,390.00 to Avison Construction Inc. of Madera, California for street paving, concrete repair, and ADA improvements in the neighborhood adjacent to Muir Elementary.
City Council Approval of Contract Change Order No. 4 in the amount of $92,731.92, with no additional working days, is necessary to compensate Avison Construction, Inc. for additional quantities due to bid item overruns, ad...