REPORT TO THE CITY COUNCIL
FROM: DENIX D. ANBIAH, PE, Director
Capital Projects Department
PAUL AMICO, PE, Director
Department of Public Utilities
BY: FRANCISCO V. MAGOS II, PE, Assistant Director
Capital Projects Department, Utilities and On-Site Project Management Division
ROBERT A. DIAZ, Project Manager
Capital Projects Department, Utilities and On-Site Project Management Division
SUBJECT
Title
Approve Contract Change Order No. 4 with Floyd Johnston Construction Company Inc. of Fresno, California in the amount of $2,924,928.00 with one hundred (100) additional working days for the Downtown Redevelopment Grant Water and Sewer Improvements Project. (Bid File 12402356) (Council District 3)
Body
RECOMMENDATIONS
Staff recommends that the City Council approve Contract Change Order No. 4 with Floyd Johnston Construction Company, Inc. of Fresno, California in the amount of $2,924,928.00, with one hundred (100) additional working days to allow for completion of domestic water improvements, sanitary sewer improvements, and to increase the Supplemental Work Contract Bid Item for the Downtown Redevelopment Grant Water and Sewer Improvements Project and authorize the Capital Projects Department Director, or designee, to sign this Contract Change Order No. 4 on the City's behalf.
EXECUTIVE SUMMARY
On June 13, 2024, a contract was awarded in the amount of $18,784,925.50 to Floyd Johnston Construction Company Inc. of Fresno, California for the Downtown Redevelopment Grant Water and Sewer Improvements Project to bring water and sewer facilities to current standards including the replacement of 14,315 linear feet of water mains, 5,576 linear feet of sanitary sewer mains, and rehabilitation of existing sewer and manhole facilities.
City Council approval of Contract Change Order No. 4, in the amount of $2,924,928.00, is recommended to support the continued progress of the project. This change order includes an extension of one hundred (100) additi...
Click here for full text