File #: ID 24-779    Version: 1 Name:
Type: Action Item Status: Passed
File created: 5/29/2024 In control: City Council
On agenda: 6/20/2024 Final action: 6/20/2024
Title: Approve Contract Change Order No. 01 in the amount of $567,390 for the installation of PG&E Rule 16 with Avison Construction Co., Inc. for the TCC Park at MLK Magnet Core Project - Project ID PW00857. (Bid File 12302905) (Council District 3)
Sponsors: Capital Projects Department
Attachments: 1. 24-779 Contract Change Order No. 01.pdf, 2. 24-779 Vicinity Map
REPORT TO THE CITY COUNCIL


FROM: RANDALL W. MORRISON PE, PMP, MCE, Director
Capital Projects Department

SCOTT L. MOZIER, PE, Director
Public Works Department

BY: KELLY YOST PE, Construction Manager
Capital Projects Department, Construction Management Division

DEVIN WILEY, Senior Engineering Inspector
Capital Projects Department, Construction Management Division

SUBJECT
Title
Approve Contract Change Order No. 01 in the amount of $567,390 for the installation of PG&E Rule 16 with Avison Construction Co., Inc. for the TCC Park at MLK Magnet Core Project - Project ID PW00857. (Bid File 12302905) (Council District 3)

Body
RECOMMENDATION

Staff recommends that the City Council approve Contract Change Order No. 01 with Avison Construction Co., Inc., which increases the contract amount by $567,390, for a revised contract total of $9,213,683, and adds thirty-two (32) additional working days for the installation of PG&E Rule 16 at the TCC Park at MLK Magnet Core project.

EXECUTIVE SUMMARY

On October 19, 2023, a contract was awarded in the amount of $8,646,293 to Avison Construction Inc., for the TCC Park at MLK Magnet Core Project. City Council approval of Contract Change Order No. 1 in the amount of $567,390 and the addition of thirty-two (32) working days of contract time will allow for the installation of the PG&E Rule 16, which will provide the electrical service connection to the new Park. The electrical service trenching and installation was not included in the scope of this project at the time of bid due to the ongoing coordination with PG&E on their service connection. The funding for this contract change order is funded by the TCC Grant funding, local Development Park Impact Fees and a one-third developer contribution for a portion of the supporting improvements, as specified in the West Creek Village Development Agreement.

BACKGROUND

On October 19, 2023, a contract was awarded in the amount of $8,646,293 to Avison Construction Inc., ...