File #: ID 23-766    Version: 1 Name:
Type: Action Item Status: Passed
File created: 5/5/2023 In control: City Council
On agenda: 5/25/2023 Final action: 5/25/2023
Title: Actions pertaining to the Waste Gas Flare Project at the Fresno-Clovis Regional Wastewater Reclamation Facility Project ID TC00159 (Bid File No. 3750) (District 3) 1. Approve Contract Change Order 04 to W.M Lyles Co., in the amount of $ 132,418.10 and two (2) additional working days.
Sponsors: Public Works Department, Department of Public Utilities
Attachments: 1. 23-766 Contract Change Order 04.pdf
REPORT TO THE CITY COUNCIL


FROM: SCOTT L. MOZIER, PE, Director
Public Works Department

BROCK D. BUCHE, PE, PLS, Director
Department of Public Utilities

BY: WILLIAM C. HERR, Assistant Director
Public Works Department, Construction Management Division

LOGAN WELCH, Senior Engineering Inspector
Public Works Department, Construction Management Division

SUBJECT
Title
Actions pertaining to the Waste Gas Flare Project at the Fresno-Clovis Regional Wastewater Reclamation Facility Project ID TC00159 (Bid File No. 3750) (District 3)
1. Approve Contract Change Order 04 to W.M Lyles Co., in the amount of $ 132,418.10 and two (2) additional working days.

Body
RECOMMENDATION

Staff recommends Council approve Contract Change Order 04 in the amount of $132,418.10 and an increase in contract time of two (2) additional days with W.M. Lyles Co. for the Waste Gas Flare Project (Project ID TC00159).

EXECUTIVE SUMMARY

Staff recommends Council approve Contract Change Order 04 in the amount of $132,418.10 and two (2) additional days for the waste Gas Flare Project to relocate a 16" digester line above ground to avoid conflict with underground utilities. Additional potholing is required for unforeseen site conditions and a water line needs to be relocated due to conflicts. An additional concrete mow curb will need to be installed at the transitions between the grass and site surfacing. None of this work was identified in the contract documents.

BACKGROUND

On December 9, 2021, a Contract was awarded in the amount of $6,395,900.00 to W.M Lyles Co., for the Waste Gas Flare Project at the Fresno-Clovis Regional Wastewater Reclamation Facility; the Notice to Proceed was issued with the start date of March 9, 2023, and completion date on April 11, 2023. There have been three (3) Contract Change Orders executed to date totaling $118,641.04, resulting in a Revised Contract Price in the amount of $6,514,541.04. There have been twenty-nine (29) days added...

Click here for full text