File #: ID 25-1109    Version: 1 Name:
Type: Action Item Status: Agenda Ready
File created: 8/6/2025 In control: City Council
On agenda: 8/28/2025 Final action:
Title: Approve Contract Change Order No. 01 with Katch Environmental Incorporated dba Katch General of Fresno, California in the amount of $203,438.20 with fourteen additional working days for the Garage 9 Renovation Project - Project ID HG00020. (Bid File 12500982) (Council District 3)
Sponsors: Capital Projects Department, Planning and Development Department
Attachments: 1. 25-1109 Construction Contract-Katch Environmental Inc. dba Katch General.pdf, 2. 25-1109 Contract Change Order No. 01.pdf, 3. 25-1109 Vicinity Map.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
REPORT TO THE CITY COUNCIL


FROM: DENIX D. ANBIAH, PE, Director
Capital Projects Department

JENNIFER K. CLARK, AICP, Director
Planning and Development Department

BY: ANTONIO BUELNA, PE, Assistant Director
Capital Projects Department, Administration Division

KELLY YOST, PE, Construction Manager
Capital Projects Department, Construction Management Division

SUBJECT
Title
Approve Contract Change Order No. 01 with Katch Environmental Incorporated dba Katch General of Fresno, California in the amount of $203,438.20 with fourteen additional working days for the Garage 9 Renovation Project - Project ID HG00020. (Bid File 12500982) (Council District 3)

Body
RECOMMENDATION

Staff recommends that the City Council approve Contract Change Order No. 01 with Katch Environmental Incorporated dba Katch General of Fresno, California in the amount of $203,438.20, with fourteen (14) additional working days to allow for completion of Architectural, Mechanical, Plumbing, and Electrical design changes for the Garage 9 Renovation Project, and authorize the Capital Projects Department Director, or designee, to sign this Contract Change Order No. 01 on behalf of the City of Fresno.

EXECUTIVE SUMMARY

On January 09, 2025, a Contract was awarded in the amount of $3,462,279.00 to Katch Environmental Incorporated dba Katch General of Fresno, California for the Garage 9 Renovation Project, to upgrade the existing site to a "move-in-ready" building space that will accommodate offices, cubicles, reception area, conference room, staff lounge, storage, and restrooms.

City Council approval of Contract Change Order No. 01 in the amount of $203,438.20, with fourteen (14) additional working days, will allow for work related to Architectural, Mechanical, Plumbing, and Electrical design changes. Approval of this proposed Contract Change Order will allow the project to move forward and provide the necessary improvements required for project completion. This in...

Click here for full text