REPORT TO THE CITY COUNCIL
FROM: DENIX D. ANBIAH, PE, Director
Capital Projects Department
PAUL AMICO, PE, Interim Director
Department of Public Utilities
BY: FRANCISCO V. MAGOS II, PE, Assistant Director
Capital Projects Department, Utilities and On-Site Project Management Division
PATRICIA DIEP, Project Manager
Capital Projects Department, Utilities and On-Site Project Management Division
SUBJECT
Title
Actions pertaining to the Butler and Eighth Trunk Sewer Repair Project (Bid File No. 12600025) (Council District 5):
1. Adopt a finding of Categorical Exemption per staff's determination, pursuant to Section 15301/Class 1 and Section 15302/Class 2 of the California Environmental Quality Act Guidelines for the Butler and Eighth Sewer Trunk Sewer Repair Project;
2. Award a construction contract in the amount of $974,912.00 to Dawson-Mauldin LLC of Selma, California, as the lowest responsive and responsible bidder for the Butler and Eighth Trunk Sewer Repair Project.
Body
RECOMMENDATIONS
Staff recommends that the City Council (1) adopt a finding of Categorical Exemption per staff's determination, pursuant to Section 15301/Class 1 and 15302/Class 2 of the California Environmental Quality Act (CEQA) Guidelines and (2) award a construction contract to Dawson-Mauldin LLC of Selma, California, in the amount of $974,912 as the lowest responsive and responsible bidder for the Butler and Eighth Trunk Sewer Repair Project (Project), and authorize the Capital Projects Director or designee to sign the standardized construction contract on behalf of the City of Fresno (City).
EXECUTIVE SUMMARY
The Capital Projects Department seeks to award a construction contract to Dawson-Mauldin LLC following a competitive bidding process that determined them to be the lowest responsive and responsible bidder in the amount of $974,912. The City discovered during routine inspection that the crown of the trunk sewer in the intersection of East Butler Av...
Click here for full text