File #: ID 24-728    Version: 1 Name:
Type: Action Item Status: Passed
File created: 5/15/2024 In control: City Council
On agenda: 6/6/2024 Final action: 6/6/2024
Title: Actions pertaining to the Calwa Townsite Phase II Water Main Replacement Project bound by Orange, Church, Cedar and Jensen Avenues, Bid File 12401802 (Council District 5 and County): 1. Adopt a finding of Categorical Exemption per staff determination pursuant to Section 15301/Class 1 (Existing Facilities) and 15302/Class 2 (Replacement or Reconstruction) of the California Environmental Quality Act (CEQA) Guidelines, for the Calwa Townsite Phase II Water Main Replacement Project, 2. Award a construction contract in the amount of $5,429,945, to West Valley Construction Company, Inc., of Fresno, California, as the lowest responsive and responsible bidder for the Phase II Water Main Replacement Project.
Sponsors: Capital Projects Department, Department of Public Utilities
Attachments: 1. 24-728 Bid Evaluation.pdf, 2. 24-728 Fiscal Impact Statement.pdf, 3. 24-728 Standardized Contract.pdf, 4. 24-728 Vicinity Map.pdf, 5. 24-728 Location Map.pdf, 6. 24-728 CEQA Environmental Assessment.pdf
REPORT TO THE CITY COUNCIL


FROM: RANDALL W. MORRISON, PE, Director
Capital Projects Department

BROCK D. BUCHE, PE, PLS, Director
Department of Public Utilities

BY: FRANCISCO V. MAGOS II, PE, Assistant Director
Capital Projects Department, Utilities and On-Site Project Management Division

ROBERT A. DIAZ, Project Manager
Capital Projects Department, Utilities and On-Site Project Management Division

SUBJECT
Title
Actions pertaining to the Calwa Townsite Phase II Water Main Replacement Project bound by Orange, Church, Cedar and Jensen Avenues, Bid File 12401802 (Council District 5 and County):
1. Adopt a finding of Categorical Exemption per staff determination pursuant to Section 15301/Class 1 (Existing Facilities) and 15302/Class 2 (Replacement or Reconstruction) of the California Environmental Quality Act (CEQA) Guidelines, for the Calwa Townsite Phase II Water Main Replacement Project,
2. Award a construction contract in the amount of $5,429,945, to West Valley Construction Company, Inc., of Fresno, California, as the lowest responsive and responsible bidder for the Phase II Water Main Replacement Project.

Body
RECOMMENDATIONS

Staff recommends City Council (1) adopt a finding of Categorical Exemption per staff's determination, pursuant to Section 15301/Class 1 (Existing Facilities) and 15302/Class 2 (Replacement or Reconstruction), of the California Environmental Quality Act (CEQA) Guidelines, and (2) award a construction contract in the amount of $5,429,945 to West Valley Construction Company, Inc., of Fresno, California, as the lowest responsive and responsible bidder for the Calwa Townsite Phase II Water Main Replacement Project (Project), and authorize the Capital Projects Director or designee to sign and execute all documents on behalf of the City of Fresno (City).

EXECUTIVE SUMMARY

The Capital Projects Department (CPD) seeks to award a water main replacement and services transfer construction contract to West Valley Construction Compan...

Click here for full text