REPORT TO THE CITY COUNCIL
FROM: RANDALL W. MORRISON, PE, Director
Capital Projects Department
BROCK D. BUCHE, PE, PLS, Director
Department of Public Utilities
BY: FRANCISCO V. MAGOS II, PE, Assistant Director
Capital Projects Department, Utilities and On-Site Project Management Division
ROBERT A. DIAZ, Project Manager
Capital Projects Department, Utilities and On-Site Project Management Division
SUBJECT
Title
Actions pertaining to the Calwa Townsite Phase II Water Main Replacement Project bound by Orange, Church, Cedar and Jensen Avenues, Bid File 12401802 (Council District 5 and County):
1. Adopt a finding of Categorical Exemption per staff determination pursuant to Section 15301/Class 1 (Existing Facilities) and 15302/Class 2 (Replacement or Reconstruction) of the California Environmental Quality Act (CEQA) Guidelines, for the Calwa Townsite Phase II Water Main Replacement Project,
2. Award a construction contract in the amount of $5,429,945, to West Valley Construction Company, Inc., of Fresno, California, as the lowest responsive and responsible bidder for the Phase II Water Main Replacement Project.
Body
RECOMMENDATIONS
Staff recommends City Council (1) adopt a finding of Categorical Exemption per staff's determination, pursuant to Section 15301/Class 1 (Existing Facilities) and 15302/Class 2 (Replacement or Reconstruction), of the California Environmental Quality Act (CEQA) Guidelines, and (2) award a construction contract in the amount of $5,429,945 to West Valley Construction Company, Inc., of Fresno, California, as the lowest responsive and responsible bidder for the Calwa Townsite Phase II Water Main Replacement Project (Project), and authorize the Capital Projects Director or designee to sign and execute all documents on behalf of the City of Fresno (City).
EXECUTIVE SUMMARY
The Capital Projects Department (CPD) seeks to award a water main replacement and services transfer construction contract to West Valley Construction Compan...