Title: Approve Contract Change Order No. 03 with Avison Construction Incorporated of Madera, California in the amount of $235,536.06 with seventeen (17) additional working days for the Chinatown Sustainable Transportation Infrastructure Project 1 and Chinatown Urban Greening Project 6. (Bid File No. 12302719) (Council District 3)
Sponsors: Capital Projects Department, Public Works Department
Attachments: 1. 25-1413 Construction Contract-Avison Construction Incorporated.pdf, 2. 25-1413 Contract Change Order No. 01.pdf, 3. 25-1413 Contract Change Order No. 02.pdf, 4. 25-1413 Contract Change Order No. 03.pdf, 5. 25-1413 Vicinity Map.pdf
REPORT TO THE CITY COUNCIL


FROM: DENIX D. ANBIAH, PE, Director
Capital Projects Department

SCOTT L. MOZIER, PE, Director
Public Works Department

BY: ANTONIO M. BUELNA, PE, Assistant Director
Capital Projects Department, Interim Construction Management Division

KELLY YOST, PE, Construction Manager
Capital Projects Department, Construction Management Division

SUBJECT
Title
Approve Contract Change Order No. 03 with Avison Construction Incorporated of Madera, California in the amount of $235,536.06 with seventeen (17) additional working days for the Chinatown Sustainable Transportation Infrastructure Project 1 and Chinatown Urban Greening Project 6. (Bid File No. 12302719) (Council District 3)

Body
RECOMMENDATION

Staff recommends that the City Council approve Contract Change Order No. 03 with Avison Construction Incorporated of Madera, California in the amount of $235,536.06 with seventeen (17) additional working days to allow for compensation of Force Account work, deletion of street lighting, alley lighting design changes, irrigation controller and design changes, installation of pedestrian barricades, modification to existing electrical improvements, adjustment of contract change order quantities, and adjustment of contract bid item quantities for the Chinatown Sustainable Transportation Infrastructure Project 1 and Chinatown Urban Greening Project 6, and authorize the Capital Projects Department Director, or designee, to sign this Contract Change Order No. 03 on behalf of the City of Fresno.

EXECUTIVE SUMMARY

On December 07, 2023, a Contract was awarded in the amount of $5,296,359.00 to Avison Construction Incorporated of Madera, California for the Chinatown Sustainable Transportation Infrastructure Project 1 and Chinatown Urban Greening Project 6, to perform concrete, asphalt, landscaping, irrigation, and lighting improvements within China Alley from Tulare Street to Ventura Street and along F Street, Mariposa Str...

Click here for full text