Legislation Details

File #: ID 26-977    Version: 1 Name:
Type: Action Item Status: Agenda Ready
File created: 7/14/2026 In control: City Council
On agenda: 8/13/2026 Final action:
Title: Approve the Third Amendment to the Professional Consultant Agreement with PCubed Associates for the FAX Maintenance Facility HVAC and Building Improvements project to provide additional design and engineering services in the amount of $161,400 with a total revised contract amount not to exceed $854,000 (Original Bid File No. 10088R)
Sponsors: Department of Transportation
Attachments: 1. 26-977 Third Amendment to PCubed Associates, Inc. Agreement, 2. 26-977 Second Amendment to PCubed Associates, Inc. Agreement, 3. 26-977 First Amendment to PCubed Associates, Inc. Agreement, 4. 26-977 Original Amendment to PCubed Associates, Inc.
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
REPORT TO THE CITY COUNCIL


FROM: GREGORY BARFIELD, M.A., Director
Department of Transportation

BY: SHANNON M. MULHALL, CASp, Projects Administrator
Department of Transportation

SHELLE O'BRIEN, Project Manager
Department of Transportation

SUBJECT
Title
Approve the Third Amendment to the Professional Consultant Agreement with PCubed Associates for the FAX Maintenance Facility HVAC and Building Improvements project to provide additional design and engineering services in the amount of $161,400 with a total revised contract amount not to exceed $854,000 (Original Bid File No. 10088R)

Body
RECOMMENDATION

Staff recommends Council approve the Third Amendment to the Professional Consultant Agreement with PCubed Associates for the FAX Maintenance Facility HVAC and Building Improvements project to provide additional design and engineering services in the amount of $161,400 with a total revised contract amount not to exceed $854,000 (Original Bid File No. 10088R).

EXECUTIVE SUMMARY

The Department of Transportation/FAX (Department) is seeking approval of this Third Amendment to the existing Professional Consulting Agreement with PCubed Associates for additional design and engineering services necessary to support the FAX Maintenance Facility HVAC and Building Improvement projects Phase I and II, at a cost of $161,400, for a revised total contract value not to exceed (NTE) $854,000. The projects include improvements to the bus maintenance building roof, HVAC equipment, gas detection system and rollup doors. This Third Amendment provides for the additional engineering and design work necessary to support ongoing construction activities, attend weekly meetings for both stages of construction for this project, provide technical responses to requests for information and equipment and material submittals. Because of the additional construction administration responsibilities due to the extended duration of the project timelines, increased engineering l...

Click here for full text