File #: ID 22-1742    Version: 1 Name:
Type: Action Item Status: Passed
File created: 11/1/2022 In control: City Council
On agenda: 11/17/2022 Final action: 11/17/2022
Title: Reject the sole bid received for the Northeast Surface Water Treatment Facility Sodium Hypochlorite Tank Replacement (Bid File 3881) (Council District 6)
Sponsors: Department of Public Utilities
Attachments: 1. Attachment 1 - Bid Evaluation and Fiscal Impact.pdf, 2. Attachment 2 - Vicinity Map.pdf
REPORT TO THE CITY COUNCIL


FROM: BROCK D. BUCHE, PE, PLS, Director
Department of Public Utilities

BY: JESUS A. GONZALEZ, PE, Public Utilities Manager
Department of Public Utilities - Utilities Planning & Engineering

SAMUEL NADORES, PE, Professional Engineer
Department of Public Utilities - Utilities Planning & Engineering

SUBJECT
Title

Reject the sole bid received for the Northeast Surface Water Treatment Facility Sodium Hypochlorite Tank Replacement (Bid File 3881) (Council District 6)

Body
RECOMMENDATION

Staff recommends that City Council reject the sole bid received for the Northeast Surface Water Treatment Facility (NESWTF) Sodium Hypochlorite Tank Replacement (Project).

EXECUTIVE SUMMARY

The Department of Public Utilities seeks to reject the bid proposal received for the Project. The proposal received in the amount of $353,897.06 was deemed "nonresponsive" due to taking exception to the specification terms and provisions.

BACKGROUND

The NESWTF has been in service since July of 2004. Over the last several years, both existing fiber reinforced plastic (FRP) sodium hypochlorite tanks at the NESWTF have shown degradation issues resulting in the increased frequency in repairs and maintenance. The sodium hypochlorite leaking from the aged tanks, due to its corrosive nature, caused damage to the supporting concrete pedestals including portions of the adjacent slab areas within the Chemical Storage Building. The scope of this Project is for the procurement only of new FRP tanks with long lead times. Repairs of the supporting concrete pedestals and installation of the tanks is to occur under a separate project.

A Notice Inviting Bids was published in the Business Journal and posted in the City's Planet Bids website on July 11, 2022. Project specifications were distributed to 20 prospective bidders. One sealed bid was received and unsealed in a public opening on August 16, 2022.

The sole bid submitted by DXP Enterprises, Inc., was 86% ab...