Title: Approve an agreement for professional engineering services with Quad Knopf Inc., dba QK, of Fresno, California for $82,930 with a $7,500 contingency, for design and construction support services for the Roeding Park Pickleball Court Project (Council District 3)
Sponsors: Public Works Department, Parks, After School, Recreation and Community Serv
Attachments: 1. 23-1073 Consultant Agreement, 2. 23-1073 Vicinity Map, 3. 23-1073 Location Map
REPORT TO THE CITY COUNCIL


FROM: SCOTT L. MOZIER, PE, Director
Public Works Department

AARON A. AGUIRRE, Director
Parks, After School, Recreation, and Community Services Department

BY: RANDALL W. MORRISON, PE, Assistant Director
Public Works Department, Engineering Division

HARLAVPREET S. BRAR, PE, Professional Engineer
Public Works Department, Site Development Project Management Section

SUBJECT
Title
Approve an agreement for professional engineering services with Quad Knopf Inc., dba QK, of Fresno, California for $82,930 with a $7,500 contingency, for design and construction support services for the Roeding Park Pickleball Court Project (Council District 3)

Body
RECOMMENDATION

Staff recommends City Council approve a consultant services agreement with Quad Knopf Inc., dba QK, of Fresno, California in the amount of $82,930, with a $7,500 contingency, for the design and preparation of construction documents for the Roeding Park Pickleball Court Project and authorize the Public Works Director or designee to execute the agreement on behalf of the City of Fresno.

EXECUTIVE SUMMARY

The City of Fresno Parks, After School, Recreation and Community Services Department (PARCS) proposes to convert three (3) existing tennis courts into new pickleball courts with upgraded lighting at Roeding Park. The project will include a community meeting to present an initial conceptual design and receive public input to inform the final design.

The contract for professional engineering design services will be funded using carryover funds from FY2023 Measure P expenditure category 1, highest-needs allocations. Council approval of the consultant agreement between the City and QK is recommended to facilitate development of plans, cost estimates, and general construction contract documents necessary to complete the project.

BACKGROUND

The PARCS Department proposes to utilize Measure P to improve the existing park facilities and enhance the park...