REPORT TO THE CITY COUNCIL
FROM: DENIX D. ANBIAH, PE, Director
Capital Projects Department
PAUL AMICO, PE, Director
Department of Public Utilities
BY: ANTONIO M. BUELNA, PE, Assistant Director
Capital Projects Department, Construction Management Division
KELLY YOST, PE, Construction Manager
Capital Projects Department, Construction Management Division
SUBJECT
Title
Approve Contract Change Order No. 02 with Emmett's Excavation Incorporated of Clovis, California in the amount of $0.00 with one hundred twenty-three (123) additional working days for the Sewer Rehab Improvements in the Area Bound by Shields, Dakota, Fruit, and Palm Avenues Project - Bid File No. 12302877. (Council District 1)
Body
RECOMMENDATION
Staff recommends that the City Council approve Contract Change Order No. 02 with Emmett's Excavation Incorporated of Clovis, California in the amount of $0.00 with one hundred twenty-three (123) additional working days to allow for the resolution of Liquidated Damages for the Sewer Rehab Improvements in the Area Bound by Shields, Dakota, Fruit, and Palm Avenues Project, and authorize the Capital Projects Department Director, or designee, to sign this Contract Change Order No. 02 on behalf of the City of Fresno.
EXECUTIVE SUMMARY
On February 01, 2024, a Contract was awarded in the amount of $5,077,159.00 to Emmett's Excavation Incorporated of Clovis, California for the Sewer Rehab Improvements in the Area Bound by Shields, Dakota, Fruit, and Palm Avenues Project to perform removal and replacement of portions of sewer mains, point repairs, installation of cured-in-place pipe (CIPP) liners in existing sewer mains, removal and replacement of existing manholes, and rehabilitation of existing manholes.
City Council approval of Contract Change Order No. 02 in the amount of $0.00 with one hundred twenty-three (123) additional working days, will allow for the resolution of Liquidated Damages. The resolution of Liquidated Damages will not i...