Title: Actions pertaining to the Fiber Optic Connection from the Fresno-Clovis Regional Wastewater Reclamation Facility to the City Hall Data Center Project (Bid File No. 12601236) (Council District 3): 1. Adopt a finding of Categorical Exemption pursuant to Section 15301/Class 1 and Section 15303/Class 3 of the California Environmental Quality Act Guidelines 2. Award a Construction Contract in the amount of $718,681.00 to DCL Technology, Incorporated of Fresno, California, as the lowest responsive and responsible bidder.
Sponsors: Capital Projects Department, Department of Public Utilities
Attachments: 1. 26-420 Environmental Assessment, 2. 26-420 Formal Procurement Evaluation, 3. 26-420 Standardized Contract, 4. 26-420 Vicinity Map, 5. 26-420 Location Map
REPORT TO THE CITY COUNCIL


FROM: DENIX D. ANBIAH, PE, Director
Capital Projects Department

PAUL AMICO, PE, Director
Department of Public Utilities

BY: CASSIE L. SCHOLZ, PE, Assistant Director
Capital Projects Department, Utilities Project Management Division

RATTAN GILL, PMP, Project Manager
Capital Projects Department, Utilities Project Management Division

SUBJECT
Title
Actions pertaining to the Fiber Optic Connection from the Fresno-Clovis Regional Wastewater Reclamation Facility to the City Hall Data Center Project (Bid File No. 12601236) (Council District 3):
1. Adopt a finding of Categorical Exemption pursuant to Section 15301/Class 1 and Section 15303/Class 3 of the California Environmental Quality Act Guidelines
2. Award a Construction Contract in the amount of $718,681.00 to DCL Technology, Incorporated of Fresno, California, as the lowest responsive and responsible bidder.

Body
RECOMMENDATIONS

Staff recommend that the City Council 1) adopt a finding of Categorical Exemption, pursuant to Section 15301/Class 1 and Section 15303/Class 3 of the California Environmental Quality Act (CEQA) Guidelines and 2) award a construction contract to DCL Technology, Incorporated (Inc.). of Fresno, California, in the amount of $718,681.00 as the lowest responsive and responsible bidder for the Fiber Connection from the Fresno-Clovis Regional Wastewater Reclamation Facility (RWRF) to the City Hall Data Center Project (Project), and authorize the Capital Projects Director or designee to sign the standardized Construction Contract on behalf of the City of Fresno (City).

EXECUTIVE SUMMARY

The Capital Projects Department seeks to award a Construction Contract to DCL Technology, Inc., following a competitive bidding process that determined them to be the lowest responsive and responsible bidder in the amount of $718,681.00. The scope of work includes validating continuity and performing repair work as necessary to the existing conduit...