REPORT TO THE CITY COUNCIL
FROM: FRANCISCO PARTRIDA, Interim Director of Aviation
Airports Department
BY: RANDOLPH ALEXANDER, Airports Project Manager
Airports Department
SUBJECT
Title
Actions pertaining to the Runway 11L-29R Reconstruction project at Fresno Yosemite International Airport (Council District 4),Bid file 12502600:
1. ***RESOLUTION - Adopt the 38th Amendment to the Annual Appropriation Resolution (AAR) No. 2025-179 appropriating $7,500,000 for the AIP 106 Reconstruction Runway Project 11L-29R for Fiscal Year 2025-2026 (Requires 5 affirmative votes) (Subject to Mayor's veto).
2. Award a Construction Contract to A. DeSilva Gates Construction-Vanguard A Joint Venture, of Dublin, California, for the Runway 11L-29R Reconstruction project at Fresno Yosemite International Airport in the amount of $98,888,888.00 (Bid File 12502600), with a notice to proceed each year contingent on FAA funding.
3. Approve a Consultant Agreement with Krazan of Fresno, California, to provide geotechnical quality assurance testing and inspection services for the Runway 11L-29R Reconstruction project at Fresno Yosemite International Airport in the amount of $1,164,070.00 for a term of three (3) years, with a notice to proceed each year contingent on FAA funding
4. Approve a Consultant Agreement with Kimley Horn for professional construction management and phasing services in the amount of $4,391,389.00 for a term of three (3) years, with a notice to proceed each year contingent on FAA funding
Body
RECOMMENDATION
Staff recommends that Council authorize the City Manager, or designee to execute a construction contract with DeSilva Gates Construction-Vanguard a Joint Venture of Dublin, California, in the amount of $98,888,888.00 (Bid File 12502600) for the Runway 11L-29R Reconstruction project (Project) at Fresno Yosemite International Airport (FAT) and approve a consultant agreement with Krazan of Fresno, California, to provide Geotechnical Quality Assurance (QA) testin...